垃圾池为垃圾焚烧发电厂主厂房最主要的结构组成部分,外型体积一般比较大,深度最深,而且一般处于厂房中部,四周均有其他建筑物.天津滨海垃圾焚烧发电厂垃圾池工程施工中,为达到垃圾池和四周建(构)筑物同时施工、节约工期的目的,经过研究,确定了钢板桩+支撑+井点降水的土方开挖支护方案、垃圾池基础底板施工方案、垃圾池上部池壁施工方案,经过施工验证,确保了施工的安全、质量和进度,同时经济效果较好.
Garbage dump is the main structural component of the main plant of MSW incineration plant. The appearance volume is generally larger and the depth is the deepest, and it is generally located in the middle of the plant with other buildings all around. Tianjin Binhai MSW Plant Garbage Tank Project , In order to achieve simultaneous construction of rubbish pools and surrounding structures and save time, the earthwork excavation and support scheme of steel sheet pile + support + well point precipitation, the construction plan of garbage basal foundation floor, rubbish The pool upper wall construction program, after construction verification, to ensure the construction safety, quality and progress, at the same time, the economic effect is better.