江北工业区在审批爱柯迪第四期项目时,为其量身定制了一套审批节点排序和一条最优审批路径,形成了一套审批专题方案全程引领项目审批快速推进机制。该项目从取得土地证到拿到施工许可证仅用了9个工作日,比土地出让合同约定提前137天开工。宁波市认真贯彻省委、省政府“最多跑一次”改革决策部署,积极探索特定区域“打包审批、集成服务”促进投资项目早审批快落地机制。爱柯迪第四期项目正
During the examination and approval of Phase I project of Aede, Phase IV, Jiangbei Industrial Zone tailored a set of approval nodes and an optimal approval route to form a set of special approval schemes to guide the project approval and rapid advance mechanism throughout the project. The project from the acquisition of land permits to get the construction permit only took 9 working days, than the land transfer contract agreed to start 137 days in advance. Ningbo City, earnestly implement the provincial party committee and government, “run at least ” reform decision-making deployment, and actively explore the specific region “package approval, integrated services ” to promote early approval of investment projects approved landing mechanism. Love the fourth phase of the project is positive