福建省重点项目水东水电站在1994年3台机组相继投产发电后,4号机组于1995年7月24日又通过了72h运行试验,正式并入省电网。装机4×2万kW的水东水电站位于闽中尤溪城关,坝址以上集雨面积3784km~2,多年平均电能2.93亿kW·h,地理条件得天独厚,是闽江干流上尤溪支流开发条件最好的一个梯级电站。该项目建设以地方为主,从
After the 3 hydropower units of the Shuidong Hydropower Project, a key project of Fujian Province, were successively put into production in 1994, Unit 4 passed a 72-hour operation test on July 24, 1995 and formally merged into the provincial grid. The 4×20,000-kw Shuidong hydropower station is located at Yuxi Chengguan in central Guizhou. The rainfall above the dam site is 3,784 km 2 and the average annual energy is 293 million kW·h. The geographical conditions are unique and it is the development condition of the Youxi tributary on the main stream of the Lancang River. One of the best cascade power stations. The construction of the project is mainly local, from