【日本《日本原子》1994年11月号第20页报道】1994年11月2日,东北电力公司所属的女川核电站2号核电机组(825MW沸水堆)首次达临界。该2号机组将于1994年12月中旬并网发电。 东北电力公司打算首先以20%的输出功率检查该核电机组系统的性能和设备功能,随后以50%和75%的输出功率进行功率提升试验,最后将于1995年的4月、5月和6月,以100%的输出功率进行试验,以确认该核电站系统和设备的性能。预计该2号机
[Japan Atom, Japan, November 1994, p. 20] On November 2, 1994, the No. 2 Nuclear Power Generating Unit (825MW boiling water reactor) belonging to the Tohcheon Nuclear Power Station of the Tohoku Electric Power Company reached criticality for the first time. The Unit 2 will be connected to the grid for power generation in mid-December 1994. Northeast Electric Power intends to first check the performance and equipment functions of the nuclear power unit system with a 20% output power, and then perform a power boost test with 50% and 75% of the output power. Finally, it will be April, May, and May of 1995. In the month, tests were conducted with 100% output power to confirm the performance of the nuclear power plant system and equipment. It is expected that the 2nd machine