对汽包的几何安装尺寸的要求 ,在所有受热面设备中是最高的。在标高找正过程中 ,实现汽包左、右侧中心等高较易做到 ,实现汽包旋转 ,达到水平度要求就不那么容易了。通过实践在汽包标高较高一侧采用塔吊 ,并施以 8t左右的力轻吊 ,另一侧用 2个 2 0t倒链提拉 ,可使汽包的不水平度控制在 0 .5mm范围内 ;汽包吊装找正后 ,与其相连的诸如下降管等外加负荷 ,将会造成汽包沉降。经验作法 :对于东方锅炉厂汽包预留 8mm ;上海锅炉厂、哈尔滨锅炉厂汽包预留 7mm ,可消除沉降误差。
The requirements for the geometric installation dimensions of the drum are the highest among all heated surface equipment. During the process of elevation calibration, it is easier to realize the contour of the left and right sides of the steam drum and to achieve the rotation of the steam drum to achieve the level requirement. Through the practice of the drum on the higher side of the tower crane, and applied to about 8t force light hanging, the other side with 2 20t chain pulling, the drum can not level control in the range of 0 .5mm Within; After the drum hoist is fixed, connected with the additional load such as down tube, will result in settlement of the drum. Experiences and practices: set aside 8mm drum for Dongfang Boiler Factory; 7mm for drum plant in Shanghai Boiler Factory and Harbin Boiler Factory, to eliminate settlement error.