摘要:在建筑排水工程中,采用柔性连接的离心铸铁管排水系统,以其独特的性能和显著的社会效益,正逐渐被广泛应用。该施工中,技术要点的控制是工程质量好坏的重要决定因素和难点。本文就柔性承插法兰连接的离心铸铁管排水系统施工特点、适用范围、工艺原理、操作工艺、操作要点、施工安全事项等方面对其施工技术进行了探讨。
关键词:离心铸铁排水管;柔性承插法兰连接
Abstract:
In the construction of drainage works, the flexible connection of centrifugal cast iron drain pipe system, with its unique performance and remarkable social benefit, and is gradually being widely used. The construction, technical key points control engineering quality are important determinants and difficulty. In this paper, a flexible socket flange connected centrifugal cast iron pipe drainage system construction characteristics, scope of application, process principle, process, operation, construction safety and other aspects of its construction technology is discussed.
Key words:
Centrifugal cast iron drainage tube; the flexible socket flange connection
中圖分类号:TU74 文献标识码:A 文章编号:
一、前言
随着建筑行业的不断发展,建筑材料的更新换代日新月异,在建筑排水工程中,传统的灰口铸铁排水管,因质脆、承压能力低,易腐蚀、水流阻力大、砂眼多、内壁容易结垢等缺点已逐渐被淘汰。塑料管道虽然在一定范围内取代了传统的灰口铸铁排水管,但塑料管材的强度低、隔音性能差,已无法满足高层、超高层建筑排水的需要。柔性连接的离心铸铁排水管,作为一种新型排水管材,完全克服了以上两种管材的弊端,以其独特的性能优点和显著的社会效益逐渐被推广应用,并成为未来排水管道产品发展的主流方向之一。
二、特点
柔性承插法兰连接的离心铸铁排水管系统具有以下突出特点:
1具有良好的抗震性、严密性等优点和一定的轴向伸缩变形及位移补偿能力。
2 管材重量比传统排水铸铁管轻、金相组织致密;系统强度更高、具有抗冲击性能。
3内外壁光滑,埋地耐腐蚀,不结垢,输送流体阻力小。
4严密性好,可大大减少了使用过程中的维修次数,延长了使用寿命(最长可达50年)。
5节能环保,离心铸铁排水管使用的原料为灰口铁,属于无毒性材料,是一种可以重复回收利用的环保排水管材,避免了环境污染。
三、适用范围
适用于工业及民用建筑中系统内压力不大于0.3Mpa、温度不高于80° C的生活排水管道、雨水管道、无侵蚀作用的工业生产废水管道和雨落管,特别适用于高层建筑排水管道系统。
四、工艺原理
该工艺柔性接头由承口、插口、法兰压盖(活套法兰)、橡胶密封圈、紧固螺栓五个部分组成,橡胶圈在螺栓、法兰压盖的作用下,呈压缩状态与管壁紧贴,起密封作用。同时,由于橡胶圈具有弹性,插口可以在承口内伸缩和偏斜,而保证不渗漏。
五、操作工艺
1 工艺流程
安装准备→管道预制加工→支架制安→干管安装→立管安装→支管安装→封堵洞口→灌水通水通球试验
2 操作工艺
2.1安装准备
1)进场材料的检查验收:
承插法兰柔性接口的排水铸铁管及其配套管件、连接件必须采用同一产品的配套管件,且具有统一的配合公差。
检查管材、管件上的标志是否有生产厂家名称或商标、执行标准的编号、名称、规格和数量;包装上是否标明产品批号、名称、接口形式、规格、生产厂名称和制造日期、批量及执行的标准、检验代号;其实物和资料应一致,同时具有质量证明书、检测报告、合格证等资料。
2)机具准备:砂轮机、台钻、电锤、套丝机、电焊机、扳手、线坠、水平尺、钢卷尺等机具和劳动力。
2.2 管道预制加工
本着安全、规范、实用、美观以及最大限度减少材料浪费的原则,根据现场实际情况绘制施工草图,按照现场尺寸以及所选用的管件本身的长度及接头的间隙计算出排水管的实际下料尺寸,再进行切割下料,切口端面应与管道轴线垂直,切口处的毛刺应清理干净,在不影响现场安装的前提下,尽可能的进行管道的地面预制,将管道通过三通、弯头、异径管等管件预制成较完整的管段,再进行安装,减少高空作业和安装工作量,预制好的管段做上编号,码放在平坦的场地,管段下方用方木垫实。
2.3管道支架的安装
1) 根据施工草图和现场的实际情况,确定支吊架的形式和数量,在地面进行支吊架的预制加工。横管支架如下图1,立管采用角钢支架。
图1 排水横管固定吊架
2)支架固定件间距:横管支架间距不大于1.5m,横管与弯头、三通、四通等连接处,接头每侧必须安装一个,管卡距接口的距离不大于30cm;立管支架净距不大于3m,楼层高度小于或等于4m时,立管可安装1个固定件。若某层立管由若干管段组成,当组成立管的单根管材长度大于1.2m时,即使楼层高度不大于4m,每根管段也要装一个固定件,位置在弯头、三通、四通等接头下方。立管底部的弯管处应设支墩或采取固定措施。
3) 安装在管道设备层内的铸铁排水干管可根据规范及设计要求做托、吊架和立管底端弯头处设砖支墩,如下图2
图2底端支墩示意图
4) 安装托、吊干管要先搭设架子,将托架、吊卡按设计坡度栽好,量好吊杆长度,将预制好的管道安装在栽设好的托架、吊架上,并固定牢固,并注意管道的各种甩口位置。
5) 排水柔性铸铁管安装时,其吊卡和防晃吊架必须符合下列要求:
①吊架间距必须保证1.2m~1.5m一个,间距不大于1.5m。
②单根管长度超过1.2m时要在该管段上设置一个吊架,水平管道转弯处也要设置吊架,并有防止管道的晃动措施。
③吊架设置位置,距离承口不大于300mm。
④排水横管吊架与所连接的立管(或与所连接的水平管)最大距离为300mm~500mm。排水立管法兰承插式接口立管管卡设在承口下方,且与接口的间距不宜大于300mm。排水横管接口应设在承口一侧,且与承口净距离不宜大于300mm。
⑤管路过长时横管起始端和末端可设防晃吊架,防晃吊架的间距不能大于12m。
2.4排水干管安装
1)管道室外暗敷设,铺设在管沟及土层内时,按施工图纸的坐标挖好管沟。若管道直埋敷设,尽量使管道直接铺设在原土层上;当管路下的原土层因承载不足需要处理时,一般挖土要比管道安装标高低150mm,以便在管道的下面回填土夯实,或做混凝土垫层。回填土或混凝土垫层做好后,再安装管道。管道可以在管沟上面做一部分预制,然后放管,找好位置和坡度以及各预留管口的方向和中心线,将管道调直、找正,然后将管段相连,管道两侧固定好,以防止回填土时使管道移位,将总出水口封堵密实,以便于进行灌水试验。注意:管道的承口要顺着来水方向安装。
2)地下室及商场等顶板下安装排水干管,首先熟悉图纸上标注的管路走向、管径、变径、标高、坡度,并兼顾各种系统管道采用综合平衡技术绘制施工草图,找好位置,按顺序进行支、吊架和管道安装,并注意管段承插口顺序和水流方向。
3)排水干管主管道穿墙、穿基础时应按下图3、图4安装。排出管与立管的连接宜采用两个45°弯头或弯曲半径不小于4倍管径的90°弯头,否则管道容易堵塞。
图3穿地下室墙壁排出管图
图4穿基础排出管安装图
2.5排水立管安装
1)根据施工图校对预留洞坐标有无差错,然后用吊通线的方法,检查立管预留洞是否满足安装立管的要求,不满足的要进行修洞。
2)立管支架在核查预留洞口无误后,用吊线及水平尺找出各支架的位置尺寸(要考虑避开排水柔性铸铁管的接口位置),统一进行编号加工,按编号就位安装。
3)安装立管时两人上下配合,一人在上一层楼板上,由管洞内投下一个绳头,下面的人将预制好的立管上半部拴牢,上拉下托将立管下部插口插入下层管承口内。
4)待下层的人把甩口及立管检查口方向找正、吊直,法兰压盖与承口法兰用螺栓拧紧并调整紧固支架上的u型卡环将管道初步固定后,上层的人用木楔、石块等将管道在楼板洞处临时卡牢,复查立管垂直度,将立管固定牢固。
5)立管安装完毕后,检测三通口中心与顶板距离,无误后固定,用不低于楼板标号的混凝土将洞灌满堵实。
6)法兰柔性管件施工时,插入端画出插入长度标记,垂直插入到标记线为止,要在承插口处留出胀缩补偿余量5mm-10mm,然后找正,见下图5。
图5
9)辅助透气管,辅助透气异型管件连接(如下图6、图7)。
图6
图7
2.6排水支管安装
1)支管安装应先搭好架子,将托架、吊架、吊卡按坡度栽好,量准吊杆尺寸,将预制好的管道托到架子上,再将支管插入立管预留口的承口内,将支管预留口尺寸找准,然后将法兰压盖与承口法兰用螺栓拧紧并固定好支管。
2)支管设在吊顶内,末端有清扫口者,应将清扫口接至上层地面上,便于清掏。
3)为了便于控制坡度,可采取先截取吊卡连接杆长度,与顶板上吊卡底座连接后再装支管。
4)支管安装完后,可将卫生洁具或设备的预留管安装到位,找准尺寸并配合土建将楼板孔洞堵严,预留管口装上临时封堵。
5)各层立管和支管安装完成后均应逐层进行灌水试验。对于标高低于各层地面的所有管口,接临时短管至该层地面上(或用橡胶堵充气堵死防止往外溢水)。排出水管口或立管检查口用法兰压盖(加垫)或橡胶堵(即管胆)进灌水试验。
2.7封堵洞口
排水管道安装完毕后,对穿墙、穿板的预留洞口及时用不低于楼板标号的混凝土将洞灌满堵实。
2.8排水系统通水试验
1)排水系统的管道、卫生器具及设备安装完成后必须进行通水试验,交工之前,在粉刷最后一道油漆前进行。
2)将室内各卫生器具的给水阀门及水龙头打开放水,排水管道及卫生器具畅通无阻,卫生器具功能使用正常,外观检查无渗漏为合格。
2.9闭(灌)水试验:
1)隐蔽或埋地的排水管道隐蔽之前必须做灌水试验。
2)按照施工图对铺设好的管道坐标、标高及预留管口尺寸进行自检,确认准确无误后即可从预留管口处灌水做闭水试验。
3)灌水试验开始,应设专人对易跑水部位进行监视检查,发现漏水及时处理。
4)灌水高度不低于底层卫生器具的上边缘或底层地面高度。
5)灌水试验可依据出户系统各厨房、卫生间、阳台分别进行。
6)选择住宅一层厨房、卫生间、阳台内排水点(甩口最高处)向系统注水,待低处卫生器具排水点及地漏内气体全部排出后封堵。
7)满水5min后,液面下降,再灌满,观察15min液面不下降各接口及管道无渗漏,经有关人员进行检查,并填写隐蔽工程验收记录,办理隐蔽工程验收手续。
8)管道系统经隐蔽验收合格后,临时封堵各预留管口,配合土建填堵孔、洞,按规定回填土。
2.10 通球试验
1)排水系统各主立管及水平干管要做通球试验,试验所用球径不小于管径的2/3,通球率达到100﹪。
2)分干管和立管进行试验,自各趟立管顶端或干管始端投入小球,均能顺利通过管道,并无卡阻现象为合格。
六、柔性铸铁管安装操作要点
1 将法兰压盖套入插口端,再套入橡胶密封圈,注意橡胶密封圈的方向性。
2将直管或管件插口端插入承口,并使插口端部与承口内底留有5mm的安装间隙。插入过程中,保证插入管的轴线与承口管的轴线在同一直线上。
3 将法兰压盖与承口法兰螺孔对正,紧固连接螺栓,紧固螺栓时应注意橡胶密封圈均匀受力,螺栓拧紧压盖时应分多次交替进行。三耳压盖螺栓应三个角同步进行,逐个逐次拧紧;四耳、六耳、八耳压盖螺栓应按对角线方向依次逐步拧紧,并注意螺栓的长度及方向一致。
4 当排水立管沿墙角敷设时,用于固定法兰压盖和橡胶密封圈的螺栓孔位置应调至墙角外侧,以便于拧紧螺栓。
5 柔性铸铁排水立管底部与排出管端部的连接,应采用两个45°弯头,或斜三通与一个45°弯头组合,并在立管底部设置支墩或支架等固定措施。
6 卫生器具排水管与柔性铸铁管的过渡采用插入式或套管式连接,并用密封材料填实到位。
七、安全事项
1 打修楼板洞眼时,应抓紧錾子,用手锤或电锤打眼,应逐渐扩孔不得用大锤打爆破眼,孔眼下不得有人停留防止砸伤。
2 打楼板洞时,上下层应临时覆盖或留人看护,打洞部位确定不得有人和物,严禁从施工孔洞中抛掷物件、材料、工具。
3 登高作业时,下面应有人扶牢梯、凳,做好监护工作,施工人员应戴好安全帽。不准往上或向下抛丢东西,只准用绳向上下吊。
4 使用电动设备时,操作者应掌握机具性能,做到安全使用。
5 使用电焊工具、要严格遵守安全防护措施,完善安全防护设备。
6 用锯条断管时,用力均匀,防止锯条折断伤人。
八、结束语
建筑排水工程中,采用柔性连接工艺的离心铸铁排水管,施工工艺简便,使用年限长,返修率低,正在得到更广泛的推广,我们期待有更好的产品应用到工程中,提高生活品质。随着社会的进步,新材料、新技术、新工艺、新设备的更新换代越来越快,推广应用四新技术是我们的责任和义务,在以后的工作中,将充分发挥我们的优势,提高我们的节能减排意识,为新技术的推广贡献我们的微薄之力!。
参考文献:
[1]赵梦海.给排水与采暖工程施工工艺標准[J].中国建筑工程总公司:中国建筑工业出版社,2004.
[2]罗定元,路志峰建筑排水用柔性接口铸铁管安装[J].中国建筑标准设计研究院,2004.
[3]建筑排水柔性接口铸铁管管道工程技术规程[J].北京:中国计划出版社,2004.
关键词:离心铸铁排水管;柔性承插法兰连接
Abstract:
In the construction of drainage works, the flexible connection of centrifugal cast iron drain pipe system, with its unique performance and remarkable social benefit, and is gradually being widely used. The construction, technical key points control engineering quality are important determinants and difficulty. In this paper, a flexible socket flange connected centrifugal cast iron pipe drainage system construction characteristics, scope of application, process principle, process, operation, construction safety and other aspects of its construction technology is discussed.
Key words:
Centrifugal cast iron drainage tube; the flexible socket flange connection
中圖分类号:TU74 文献标识码:A 文章编号:
一、前言
随着建筑行业的不断发展,建筑材料的更新换代日新月异,在建筑排水工程中,传统的灰口铸铁排水管,因质脆、承压能力低,易腐蚀、水流阻力大、砂眼多、内壁容易结垢等缺点已逐渐被淘汰。塑料管道虽然在一定范围内取代了传统的灰口铸铁排水管,但塑料管材的强度低、隔音性能差,已无法满足高层、超高层建筑排水的需要。柔性连接的离心铸铁排水管,作为一种新型排水管材,完全克服了以上两种管材的弊端,以其独特的性能优点和显著的社会效益逐渐被推广应用,并成为未来排水管道产品发展的主流方向之一。
二、特点
柔性承插法兰连接的离心铸铁排水管系统具有以下突出特点:
1具有良好的抗震性、严密性等优点和一定的轴向伸缩变形及位移补偿能力。
2 管材重量比传统排水铸铁管轻、金相组织致密;系统强度更高、具有抗冲击性能。
3内外壁光滑,埋地耐腐蚀,不结垢,输送流体阻力小。
4严密性好,可大大减少了使用过程中的维修次数,延长了使用寿命(最长可达50年)。
5节能环保,离心铸铁排水管使用的原料为灰口铁,属于无毒性材料,是一种可以重复回收利用的环保排水管材,避免了环境污染。
三、适用范围
适用于工业及民用建筑中系统内压力不大于0.3Mpa、温度不高于80° C的生活排水管道、雨水管道、无侵蚀作用的工业生产废水管道和雨落管,特别适用于高层建筑排水管道系统。
四、工艺原理
该工艺柔性接头由承口、插口、法兰压盖(活套法兰)、橡胶密封圈、紧固螺栓五个部分组成,橡胶圈在螺栓、法兰压盖的作用下,呈压缩状态与管壁紧贴,起密封作用。同时,由于橡胶圈具有弹性,插口可以在承口内伸缩和偏斜,而保证不渗漏。
五、操作工艺
1 工艺流程
安装准备→管道预制加工→支架制安→干管安装→立管安装→支管安装→封堵洞口→灌水通水通球试验
2 操作工艺
2.1安装准备
1)进场材料的检查验收:
承插法兰柔性接口的排水铸铁管及其配套管件、连接件必须采用同一产品的配套管件,且具有统一的配合公差。
检查管材、管件上的标志是否有生产厂家名称或商标、执行标准的编号、名称、规格和数量;包装上是否标明产品批号、名称、接口形式、规格、生产厂名称和制造日期、批量及执行的标准、检验代号;其实物和资料应一致,同时具有质量证明书、检测报告、合格证等资料。
2)机具准备:砂轮机、台钻、电锤、套丝机、电焊机、扳手、线坠、水平尺、钢卷尺等机具和劳动力。
2.2 管道预制加工
本着安全、规范、实用、美观以及最大限度减少材料浪费的原则,根据现场实际情况绘制施工草图,按照现场尺寸以及所选用的管件本身的长度及接头的间隙计算出排水管的实际下料尺寸,再进行切割下料,切口端面应与管道轴线垂直,切口处的毛刺应清理干净,在不影响现场安装的前提下,尽可能的进行管道的地面预制,将管道通过三通、弯头、异径管等管件预制成较完整的管段,再进行安装,减少高空作业和安装工作量,预制好的管段做上编号,码放在平坦的场地,管段下方用方木垫实。
2.3管道支架的安装
1) 根据施工草图和现场的实际情况,确定支吊架的形式和数量,在地面进行支吊架的预制加工。横管支架如下图1,立管采用角钢支架。
图1 排水横管固定吊架
2)支架固定件间距:横管支架间距不大于1.5m,横管与弯头、三通、四通等连接处,接头每侧必须安装一个,管卡距接口的距离不大于30cm;立管支架净距不大于3m,楼层高度小于或等于4m时,立管可安装1个固定件。若某层立管由若干管段组成,当组成立管的单根管材长度大于1.2m时,即使楼层高度不大于4m,每根管段也要装一个固定件,位置在弯头、三通、四通等接头下方。立管底部的弯管处应设支墩或采取固定措施。
3) 安装在管道设备层内的铸铁排水干管可根据规范及设计要求做托、吊架和立管底端弯头处设砖支墩,如下图2
图2底端支墩示意图
4) 安装托、吊干管要先搭设架子,将托架、吊卡按设计坡度栽好,量好吊杆长度,将预制好的管道安装在栽设好的托架、吊架上,并固定牢固,并注意管道的各种甩口位置。
5) 排水柔性铸铁管安装时,其吊卡和防晃吊架必须符合下列要求:
①吊架间距必须保证1.2m~1.5m一个,间距不大于1.5m。
②单根管长度超过1.2m时要在该管段上设置一个吊架,水平管道转弯处也要设置吊架,并有防止管道的晃动措施。
③吊架设置位置,距离承口不大于300mm。
④排水横管吊架与所连接的立管(或与所连接的水平管)最大距离为300mm~500mm。排水立管法兰承插式接口立管管卡设在承口下方,且与接口的间距不宜大于300mm。排水横管接口应设在承口一侧,且与承口净距离不宜大于300mm。
⑤管路过长时横管起始端和末端可设防晃吊架,防晃吊架的间距不能大于12m。
2.4排水干管安装
1)管道室外暗敷设,铺设在管沟及土层内时,按施工图纸的坐标挖好管沟。若管道直埋敷设,尽量使管道直接铺设在原土层上;当管路下的原土层因承载不足需要处理时,一般挖土要比管道安装标高低150mm,以便在管道的下面回填土夯实,或做混凝土垫层。回填土或混凝土垫层做好后,再安装管道。管道可以在管沟上面做一部分预制,然后放管,找好位置和坡度以及各预留管口的方向和中心线,将管道调直、找正,然后将管段相连,管道两侧固定好,以防止回填土时使管道移位,将总出水口封堵密实,以便于进行灌水试验。注意:管道的承口要顺着来水方向安装。
2)地下室及商场等顶板下安装排水干管,首先熟悉图纸上标注的管路走向、管径、变径、标高、坡度,并兼顾各种系统管道采用综合平衡技术绘制施工草图,找好位置,按顺序进行支、吊架和管道安装,并注意管段承插口顺序和水流方向。
3)排水干管主管道穿墙、穿基础时应按下图3、图4安装。排出管与立管的连接宜采用两个45°弯头或弯曲半径不小于4倍管径的90°弯头,否则管道容易堵塞。
图3穿地下室墙壁排出管图
图4穿基础排出管安装图
2.5排水立管安装
1)根据施工图校对预留洞坐标有无差错,然后用吊通线的方法,检查立管预留洞是否满足安装立管的要求,不满足的要进行修洞。
2)立管支架在核查预留洞口无误后,用吊线及水平尺找出各支架的位置尺寸(要考虑避开排水柔性铸铁管的接口位置),统一进行编号加工,按编号就位安装。
3)安装立管时两人上下配合,一人在上一层楼板上,由管洞内投下一个绳头,下面的人将预制好的立管上半部拴牢,上拉下托将立管下部插口插入下层管承口内。
4)待下层的人把甩口及立管检查口方向找正、吊直,法兰压盖与承口法兰用螺栓拧紧并调整紧固支架上的u型卡环将管道初步固定后,上层的人用木楔、石块等将管道在楼板洞处临时卡牢,复查立管垂直度,将立管固定牢固。
5)立管安装完毕后,检测三通口中心与顶板距离,无误后固定,用不低于楼板标号的混凝土将洞灌满堵实。
6)法兰柔性管件施工时,插入端画出插入长度标记,垂直插入到标记线为止,要在承插口处留出胀缩补偿余量5mm-10mm,然后找正,见下图5。
图5
9)辅助透气管,辅助透气异型管件连接(如下图6、图7)。
图6
图7
2.6排水支管安装
1)支管安装应先搭好架子,将托架、吊架、吊卡按坡度栽好,量准吊杆尺寸,将预制好的管道托到架子上,再将支管插入立管预留口的承口内,将支管预留口尺寸找准,然后将法兰压盖与承口法兰用螺栓拧紧并固定好支管。
2)支管设在吊顶内,末端有清扫口者,应将清扫口接至上层地面上,便于清掏。
3)为了便于控制坡度,可采取先截取吊卡连接杆长度,与顶板上吊卡底座连接后再装支管。
4)支管安装完后,可将卫生洁具或设备的预留管安装到位,找准尺寸并配合土建将楼板孔洞堵严,预留管口装上临时封堵。
5)各层立管和支管安装完成后均应逐层进行灌水试验。对于标高低于各层地面的所有管口,接临时短管至该层地面上(或用橡胶堵充气堵死防止往外溢水)。排出水管口或立管检查口用法兰压盖(加垫)或橡胶堵(即管胆)进灌水试验。
2.7封堵洞口
排水管道安装完毕后,对穿墙、穿板的预留洞口及时用不低于楼板标号的混凝土将洞灌满堵实。
2.8排水系统通水试验
1)排水系统的管道、卫生器具及设备安装完成后必须进行通水试验,交工之前,在粉刷最后一道油漆前进行。
2)将室内各卫生器具的给水阀门及水龙头打开放水,排水管道及卫生器具畅通无阻,卫生器具功能使用正常,外观检查无渗漏为合格。
2.9闭(灌)水试验:
1)隐蔽或埋地的排水管道隐蔽之前必须做灌水试验。
2)按照施工图对铺设好的管道坐标、标高及预留管口尺寸进行自检,确认准确无误后即可从预留管口处灌水做闭水试验。
3)灌水试验开始,应设专人对易跑水部位进行监视检查,发现漏水及时处理。
4)灌水高度不低于底层卫生器具的上边缘或底层地面高度。
5)灌水试验可依据出户系统各厨房、卫生间、阳台分别进行。
6)选择住宅一层厨房、卫生间、阳台内排水点(甩口最高处)向系统注水,待低处卫生器具排水点及地漏内气体全部排出后封堵。
7)满水5min后,液面下降,再灌满,观察15min液面不下降各接口及管道无渗漏,经有关人员进行检查,并填写隐蔽工程验收记录,办理隐蔽工程验收手续。
8)管道系统经隐蔽验收合格后,临时封堵各预留管口,配合土建填堵孔、洞,按规定回填土。
2.10 通球试验
1)排水系统各主立管及水平干管要做通球试验,试验所用球径不小于管径的2/3,通球率达到100﹪。
2)分干管和立管进行试验,自各趟立管顶端或干管始端投入小球,均能顺利通过管道,并无卡阻现象为合格。
六、柔性铸铁管安装操作要点
1 将法兰压盖套入插口端,再套入橡胶密封圈,注意橡胶密封圈的方向性。
2将直管或管件插口端插入承口,并使插口端部与承口内底留有5mm的安装间隙。插入过程中,保证插入管的轴线与承口管的轴线在同一直线上。
3 将法兰压盖与承口法兰螺孔对正,紧固连接螺栓,紧固螺栓时应注意橡胶密封圈均匀受力,螺栓拧紧压盖时应分多次交替进行。三耳压盖螺栓应三个角同步进行,逐个逐次拧紧;四耳、六耳、八耳压盖螺栓应按对角线方向依次逐步拧紧,并注意螺栓的长度及方向一致。
4 当排水立管沿墙角敷设时,用于固定法兰压盖和橡胶密封圈的螺栓孔位置应调至墙角外侧,以便于拧紧螺栓。
5 柔性铸铁排水立管底部与排出管端部的连接,应采用两个45°弯头,或斜三通与一个45°弯头组合,并在立管底部设置支墩或支架等固定措施。
6 卫生器具排水管与柔性铸铁管的过渡采用插入式或套管式连接,并用密封材料填实到位。
七、安全事项
1 打修楼板洞眼时,应抓紧錾子,用手锤或电锤打眼,应逐渐扩孔不得用大锤打爆破眼,孔眼下不得有人停留防止砸伤。
2 打楼板洞时,上下层应临时覆盖或留人看护,打洞部位确定不得有人和物,严禁从施工孔洞中抛掷物件、材料、工具。
3 登高作业时,下面应有人扶牢梯、凳,做好监护工作,施工人员应戴好安全帽。不准往上或向下抛丢东西,只准用绳向上下吊。
4 使用电动设备时,操作者应掌握机具性能,做到安全使用。
5 使用电焊工具、要严格遵守安全防护措施,完善安全防护设备。
6 用锯条断管时,用力均匀,防止锯条折断伤人。
八、结束语
建筑排水工程中,采用柔性连接工艺的离心铸铁排水管,施工工艺简便,使用年限长,返修率低,正在得到更广泛的推广,我们期待有更好的产品应用到工程中,提高生活品质。随着社会的进步,新材料、新技术、新工艺、新设备的更新换代越来越快,推广应用四新技术是我们的责任和义务,在以后的工作中,将充分发挥我们的优势,提高我们的节能减排意识,为新技术的推广贡献我们的微薄之力!。