无锡江南无线电器材厂不吃“大锅饭”,在建筑安装工地改行“小包工”和“班组综合超额计件工资”制,使已经延误工期的彩色电视线性集成电路工程进度大大加快,一个月完成的工作量比过去两个月干的还多。 这项引进工程,是同陕西咸阳彩色电视显象管工程配套的。全部建设后,可为五百万台各类彩色电视机提供集成电路部件。土建工程从去年六月全面动工,由于准备工作较差、施工条件不大好,今年以来又连
Wuxi Jiangnan Radio Equipment Factory does not eat “big pot rice” and diverts “small contractors” and “comprehensive comprehensive piece-rate wages” to the construction and installation site, which greatly speeds up the progress of the color television linear integrated circuit project that has been delayed and completes one month. More than the past two months. The introduction of this project is in line with the color television picture tube project in Xianyang, Shaanxi. After the entire construction, it can provide integrated circuit components for 5 million sets of color TV sets. The civil engineering project started in June last year. Due to poor preparation and poor construction conditions, this year it has