札幌市内铁路的高架化工程始于 1 978年 ,至 1 991年完成了札幌站至琴似站的高架化改造。 1 992年至1 996年又实现了“新川高架”。这里介绍的是始于1 996年的八轩站至新琴似站的高架及复线改造工程 ,即“新川高架”的延长部分。高架区间占地宽 1 2~1 8m ,且以既有线中线为中
The viaduct project of the Sapporo Railroad started in 1978 and completed the viaduct transformation from Sapporo Station to Kinko Station in 1991. From 1992 to 1996, the “Sinchon Elevated” was realized again. Here is the viaduct and double-track reconstruction project from VIII Hinaton to Sinqin-like stations starting from 1996, the extension of “Sinchon Elevated”. The elevated section covers an area of 12 ~ 18m, and is centered on the existing center line