葛州坝换流站引进的7台换流变压器,每台运输重量为245t,运输尺寸(长8.33m,宽5.39m,高4.96m)已超过铁路限值,根据换流站所处位置采用了水路运输。变压器由荷兰鹿特丹港运至上海;在上海换装内河驳船经黄浦江、长江直达葛州坝鹅石予港码头,然后用大型平板汽车运至换流站内。
Gezhouba converter station introduced seven converter transformers, each transport weight of 245t, transport dimensions (length 8.33m, width 5.39m, height 4.96m) has exceeded the railway limit, according to the location of the converter station Water transport. The transformers are transported to Shanghai by the port of Rotterdam, the Netherlands; the river barges in Shanghai are transited by the Huangpu River and the Gejiang dam goes to the port of Gezhou in the Yangtze River, and then transported to the converter station by a large flat-panel car.