通过靖安高速公路路面(延安段)MII3标合同段水泥稳定碎石基层的机械化施工,从工程实际出发,着重就机械化施工机械配备、组合以及水泥稳定碎石基层拌和、运输、摊铺、碾压、养生等施工组织和施工工序作了详细介绍。并且在实际施工中把施工技术规范、施工设计内容与具体施工有机结合,提出了提高水泥稳定碎石基层质量的施工建议。
Through mechanized construction of cement stabilized aggregate at MII3 contract section of Jing’an Expressway pavement (Yan’an Section), from the actual project practice, we will focus on mechanized construction machinery equipment, combination and cement stabilized gravel mixing, transportation, paving, Pressure, health and other construction organizations and construction processes were described in detail. And in the actual construction of the construction specifications, construction design content and the specific combination of construction, put forward to improve the quality of cement stabilized gravel construction recommendations.