我厂26立方米小高炉在76年大修期间,采用了磷酸盐炭捣混凝土和磷酸盐混凝土炉衬,並采用了现场浇灌的新工艺。全部筑炉时间仅用了4天。高炉于76年6月29日点火开炉,至78年3月1日因缺焦停炉大修。这期间因缺焦、停电封炉5次,106天(其中二次重新装炉点火)。高炉第二代炉令实际生产了十七个月,而第一代炉令实际生产了十二个月。一、耐火混凝土高炉内衬的结构及设计(见附图一) 在内衬材质上,我们根据山西灵石钢铁厂和江宁钢铁厂、金坛钢铁厂陡用的磷酸盐耐
I plant 26 cubic meters of small blast furnace overhaul in 76 years, the use of phosphate crushed concrete and phosphate concrete lining, and the use of a new process of watering. It took only 4 days for all the furnaces to be built. The blast furnace was ignited on June 29, 2006 and was shut down for overhaul on March 1, 1978. During this period due to lack of coke, power off the stove 5 times, 106 days (of which the second re-furnace ignition). The second generation of blast furnaces actually produced for 17 months, while the first generation of furnaces actually produced for 12 months. First, the structure and design of refractory concrete blast furnace lining (see Figure 1) In lining material, we based on Shanxi Lingshi Steel Plant and Jiangning Iron and Steel Plant, Jintan Iron and Steel Plant steep use of phosphate resistance