日本神户公共道路株式会社完成了一条双车道公路,全长为8.9km。这条公路的NuNobiki公路隧道(全长为2.7km)以50°交叉角穿过日本新干线高速铁路神户隧道底部的风化花岗岩地层。两条隧道交叉处的上下距离为15.5m。对于这个交叉处的施工要求是,上部铁路隧道的允许下沉量为3mm。为达到这要求,日本京都大学荣誉教授S,村山先生提出了“岩石顶板冻结法”,即在冻结的岩石顶板保护下进行隧道的挖掘工作。这种方法被此隧道工程
Kobe, Japan Public Road Co., Ltd. completed a two-lane highway, a total length of 8.9km. The NuNobiki highway tunnel (2.7km in total length) crosses the weathered granite formation at the bottom of the Kobe tunnel of the Shinkansen high-speed line of Japan at a cross angle of 50 °. The distance between two tunnels is 15.5m. The construction requirement for this intersection is that the allowed subsidence of the upper railroad tunnel is 3 mm. In order to meet this demand, Professor Saku Murayama, an honorary professor at Kyoto University in Japan, proposed the “Rock Freezing Method”, which is to excavate the tunnel under the protection of a frozen rock roof. This method is the tunnel project