某钢厂炼钢车间新增一台120t转炉,因原车间未预留炉位,需对厂房进行大规模拆除还建,施工与生产严重交叉,施工环境异常复杂,现场作业面狭窄,施工难度非常大。项目部结合图纸对现场进行了系统性的研究分析,采取分段分区施工、重点突破、全面统筹协调的策略组织施工,在保证生产的前提下,顺利地完成了施工任务。
A new 120t converter was added to a steelmaking plant in a steel mill. Due to the furnace was not reserved in the original workshop, large-scale demolition of the factory building was required. The construction and production were seriously cross-linked. The construction environment was extremely complicated and the site for operation was narrow with a very difficult construction Big. Based on the drawings, the project department conducted a systematic research and analysis on the site and adopted a sub-district construction and key breakthroughs to comprehensively and overall coordinate and coordinate the construction of the strategy. Under the precondition of ensuring production, the construction project was successfully completed.