论文部分内容阅读
山口水库坝基及坝肩防渗的主要方式为在坝基设截水槽和坝基、坝肩帷幕灌浆。在灌浆施工中,出现了如初始压力大,土坝坝体内成孔困难等情况,经过邀请省内知名专家咨询,业主、监理、设计、地质及施工单位多次商讨,共同努力,先后解决了这些问题,在探讨和研究中较好的完成了山口水库帷幕灌浆等工程。
The main way of seepage control of dam foundation and dam abutment of Shankou Reservoir is that the dam foundation is set with cutoff trough and dam foundation and dam shoulder curtain grouting. In the grouting construction, such as the initial pressure is large, the earth dam body into holes difficult situation, after the invitation of well-known experts in the province consulting, owners, supervisors, design, geological and construction units to discuss many times, work together, has solved These problems, in the discussion and research better completed the Yamaguchi reservoir curtain grouting and other projects.