历年修堤工程中各级领导对于保证工程质量一般是重视的,并曾付出很大努力,取得了相当成效,但是也有个别单位对于保证工程质量的意义认识不足,因而忽视了工程质量,并造成严重恶果。本文揭发的博爱县忽视工程质量的情况即是一例。该段在设计时不但缺乏调查研究,而在施工中发现士料含水量过大时,也不及时向上级报告,竟用脚踏代替打硪,并且随便变更工程计划,减少土方数量。河南河务局及新乡修防处发现了这一问题后,及时采取措施进行通报批评、纠正是非常正确的。本刊现将河南河务局的通报摘要发表,希望各地通过这一事件,教育全体职工并结合自己的工作认真检查一次所修工程的质量,以杜绝类似事件的再次发生,胜利地完成今年的修堤任务。
In the past years, the leaders at all levels of the dike restoration project have generally attached great importance to ensuring the quality of the project. Great efforts have been made and great achievements have been made. However, there are also some units that fail to understand the meaning of guaranteeing the project quality, thus neglecting the quality of the project and causing Serious consequences. The situation in which the quality of construction is neglected in this county is an example. This section is not only lack of research in the design, construction materials found in the water content is too large, it does not promptly report to the superiors, actually replaced with a foot instead of shuttlecock, and casually change the project to reduce the number of earthwork. After discovering this issue, the Henan River Bureau and Xinxiang Amendment Office took prompt measures to criticize and rectify them. It is very correct. This issue shows a summary of the circulars from the Henan River Commission Bureau. I hope that through this incident, I wish to educate all the staff and workers and carefully check the quality of the repaired projects in light of their work so as to prevent the recurrence of similar incidents and successfully complete this year’s Repair dike mission.