利用世界银行贷款的太湖防洪项目,涉及江苏、上海、浙江二省一市的13个县,需征用土地2.8万亩,临时占地4.7万亩,拆迁房屋80万平方米,动迁20313人。该项目的征地、拆迁补偿费为2.5亿元,占工程总投资的12%左右。自1991年开工以来,已完成征地2.2万亩,占计划数的80%;拆迁房屋38万平方米,占计戈数的50%。 移民安置工作由于采取了“前期补偿、补助,后期扶持”和实施优惠政策的办法,使移民
The World Bank-financed Taihu Flood Control Project, which involves 13 counties in Jiangsu, Shanghai and Zhejiang provinces and cities, requires the acquisition of 28,000 mu of land, the temporary occupation of 47,000 mu, the demolition of houses of 800,000 square meters, and the relocation of 20,313 people. The compensation for land acquisition and house demolition for this project is 250 million yuan, accounting for about 12% of the total project investment. Since the start of construction in 1991, 22,000 mu of land has been acquired, accounting for 80% of the planned number; 380,000 square meters of houses have been demolished, accounting for 50% of the plan’s number. The resettlement work has made immigration due to the adoption of “preliminary compensation, subsidies, and later support” and the implementation of preferential policies.