以直径71.2m索穹顶工程为对象,介绍了索穹顶施工技术的重点及难点问题,即拉索下料尺寸的控制、结构的安装方法、结构的张拉成型方法。在总结国外类似工程的施工经验基础上,首次提出了地面整体拼装、整体同步提升外脊索和外斜索的安装方法,减少了高空作业量,保证了施工安全。根据索穹顶结构为柔性结构且具有多个对称轴的特点,制定了分级分批张拉的施工方法,完成了对索穹顶结构的张拉施工,从监测数据看,施工完毕以后的位形和设计位形基本一致。
Taking the 71.2m diameter cable dome project as an example, the key points and difficult problems of cable dome construction technology are introduced, that is, the control of the size of cable pull, the installation method of the structure and the tension forming method of the structure. On the basis of summarizing the construction experience of similar projects in foreign countries, the ground assembly as a whole was first proposed to improve the installation method of external ridges and external ridges simultaneously, reducing the workload at high altitude and ensuring the construction safety. According to the structure of cable dome is flexible and has many symmetrical axes, the construction method of grading and batch tensioning is established and the tension construction of cable dome structure is completed. According to the monitoring data, Basic design consistent shape.