论文部分内容阅读
本文结合吉布洛电站厂房上游吊车梁采用吊模施工的计算、设计及施工,分析了采用吊模施工的优势及具体过程,对吊车梁等高空作业面模板施工技术改进具有一定的推进作用。
In this paper, the calculation, design and construction of the crane girder used in the crane beam at the upper reaches of the Jibuluo Power Plant are analyzed. The advantages and the specific process of the construction of the crane crane are analyzed, which will promote the construction technology of the crane girder and other working surfaces.