长寿天然气净化分厂400×104 m 3/d 装置于1998 年3 月25 日进气试生产一次成功,经过8 个月的试生产,于1998 年11 月7~10 日一次性通过四川石油管理局组织的72 h 满负荷性能考核。本文着重对该厂工艺装置(脱硫、脱水、回收)的试运状况进行了总结,同时对装置特点及存在的问题进行了评析。
Changshou Natural Gas Purification Plant 400 × 104m 3 / d unit on March 25, 1998 into the trial production of a success, after eight months of trial production, in November 1998 from 7 to 10 one-time through the Sichuan Petroleum Administration Bureau of 72 h at full capacity performance assessment. This article focuses on the factory process equipment (desulfurization, dehydration, recycling) the status of the commissioning of the trial were summarized, at the same time, the characteristics of the device and the existing problems were analyzed.