阜新海州露天矿是苏联援建的156项重点工程之一,是新中国建设的第一个大型现代化露天煤矿,地质储量17988.8万吨。该工程于1950年4月破土开工,1953年7月1日正式投产,建设工期40个月,比计划提前6个月竣工,设计能力300万吨/年。海州露天煤矿东西长4公里,南北宽2公里,现垂深250米,总面积30平方公里,是当时亚洲最大的机械化露天煤矿,为共和国经济建设作出了巨大贡献。海州露天煤矿移交生产时共完成基建总投资
Fuxin Haizhou open pit mine is one of the 156 key projects aided by the Soviet Union and is the first large-scale modern open pit coal mine built in new China with a geological reserve of 179.888 million tons. The project was started in April 1950 and was officially put into operation on July 1, 1953. The construction period is 40 months, completed 6 months ahead of schedule and the designed capacity is 3 million tons / year. Haizhou open-pit coal mine 4 km long east-west, 2 km north-south width, now 250 meters deep, with a total area of 30 square kilometers, was the largest mechanized open-pit coal mine in Asia at that time, for the Republic of economic construction has made tremendous contributions. Haizhou open pit coal mine completed the transfer of production of a total investment in infrastructure