浙江省电厂近几年分散控制系统发生的故障有共用模块、信号模块、输入/输出模块故障;主控制器故障;模拟量信号漂移,DCS故障诊断功能设置不全、未设置或设置错误故障;软件不成熟、通信阻塞、软件安装或操作不当故障;电源模块和电源开关故障、电源系统接触不良、UPS功能失效等故障。为提高热工自动化系统的可靠性,建议完善该系统的软、硬件;规范热工试验;加强检修和运行维护的管理。
Zhejiang power plant in recent years, decentralized control system failures have common modules, signal modules, input / output module failure; main controller failure; analog signal drift, DCS fault diagnosis function is not set, set or set the error failure; software Immaturity, communication blockage, software installation or improper operation; power module and power switch failure, poor power system contact, UPS failure and other failures. In order to improve the reliability of the thermal automation system, it is suggested to improve the software and hardware of the system; to standardize the thermal test; and to strengthen the management of maintenance and operation and maintenance.