西枝江水文自动测报系统。系统土建及信道部分于一九八一年动工兴建,一九八三年安装及调试运行,一九八四年考核运行,一九八五年通过鉴定投产。系统总投资为110万元。系统建成以后,使我们改变了以住收集雨量、水位数据的常规方法,从而大大减轻了劳动强度,更重要的是能及时收集水文情报,收集时间以原来的几小时缩短为几分钟,这就为防汛水情预报多争取到几小时的预见期,有利于三防部门各级领导及早作出防洪决策,实施正确的指挥,组织人力物力进行抗洪抢险,安排居民搬出险区,搬迁低水物资,避免或减轻
Xizi Jiang hydrological automatic reporting system. The system of civil engineering and channel construction started construction in 1981, installation and commissioning in 1983, operation in 1984 and accreditation in 1985. The total investment of the system is 1.1 million yuan. After the completion of the system, we have changed the conventional method of collecting rainfall and water level data, which has greatly reduced the labor intensity. More importantly, it can collect hydrological information in time and the collection time can be shortened from a few hours to a few minutes. For flood control forecasting more than a few hours to reach the expected period is conducive to the leaders of the three defense departments at all levels to make early flood control decisions, the implementation of the correct command, organize manpower and resources for flood control and rescue, arrange residents out of the danger zone, relocation of low-water materials, Avoid or mitigate