【摘要】河南煤化集团投资公司洗选厂工程中精煤仓、原煤仓工程漏斗部分耐磨料的施工,耐磨层施工前,原有混凝土基层已达到最终硬化强度,保证耐磨层和原有混凝土基层粘接牢固,形成有机整体,其耐磨料施工主要从基层、铺设钢筋网、涂刷界面、耐磨料搅拌、抹灰、压光,养护等方面确保施工质量达到预期效果。
【关键词】耐磨料基层;施工;养护
High-strength wear-resistant material construction program
Chen Xiao-min
(Henan Cheong Construction Engineering Co., LtdHebiHenan458000)
【Abstract】Henan Province Coal Group investment firm in coal washing plant engineering positions, coal storage hopper part of the project the construction of wear-resistant materials, wear-resistant layer of pre-construction, the original concrete base has hardened to achieve the ultimate strength, wear-resistant layer to ensure that the original concrete base and sticky connected firmly to form an organic whole, its wear-resistant construction materials, mainly from the grassroots, the laying of steel mesh, brushing interface, wear-resistant material mixing, plastering, calendar, maintenance, etc. to ensure the quality of construction to achieve the desired results.
【Key words】Wear-resistant material grassroots;Construction;Conservation
1. 概述
我单位所施工的河南煤化集团投资公司洗选厂工程中精煤仓、原煤仓工程漏斗部分耐磨料,首先在进行耐磨层施工前,对原有混凝土基层已施工完超过28天,达到最终硬化强度,保证耐磨层和原有混凝土基层粘接牢固,形成有机整体,采取以下三个必要的工艺准备:基层处理、铺设钢筋网、涂刷界面剂。
2. 基层处理
界面基層处理主要注意三点:(1)粗糙程度,基层越粗糙,界面结合面积越大,合力越大,抵抗剪切破坏的能力就越强,所以要对基层进行凿毛。(2)完好程度,指粘接面受损伤的程度,损伤越轻,内部产生缺陷越少,粘接性能越好,所以要对基础表面如有疏松部位应予剔除。(3)洁净程度,减少杂质,有利于提高粘接强度。所以要用压力水冲洗清理基础表面,不得有浮浆、浮灰和脱模剂等杂物。
3. 铺设钢筋网
为了保证抗磨层与混凝土基层的整体性,减少大面积抹灰造成的抗磨层收缩,增大约束,防止产生空鼓和裂纹,在基层表面需埋设钢筋网。
混凝土基层钻孔深50~70mm,孔径12mm;用MS-502钢筋锚固料锚固5~6mm钢筋钉,外露15~30mm(设计抗磨层厚度的1/3),钢筋钉之间的间距300mm,呈梅花形分布。或直接钻孔孔径6mm,孔深50mm,将钢筋钉直接砸入即可。
耐磨层厚度小于40mm时,只需载埋“L”钢筋钉即可进行下步施工。当耐磨层厚度不大于40mm时,在“L”钢筋钉的顶端需用5~6mm盘条焊接成网。
“L”钢筋钉载埋方法见图1。
4. 涂刷界面剂
4.1施工前2小时充分湿润基础表面,施工时将浮水吸干。
4.2将MS-702专用界面处理剂均匀涂刷在已处理好的混凝土基础表面,不能漏刷。
5. 耐磨料搅拌
耐磨料拌合时,加水量应按随货提供的产品合格证上的推存用水量加入,搅拌均匀,用水量可根据环境条件及实际工程情况适当调整,拌合用水应符合现行《混凝土拌合用水标准》的规定;
高强耐磨料可采用机械搅拌,建议采用强制式搅拌机进行机械搅拌,可以提高施工效率,搅拌时间一般为2~3分钟,保证搅拌充分均匀,施工效果更好。现场加水量为13%~14%加水搅拌,稠度以适合施工为宜,搅拌位置尽量靠近施工位置,以利施工的连续进行。从加水搅拌到施工完毕应控制在40分钟内为宜,因此应保证每次搅拌量与施工速度相匹配。
现场使用时,严禁在高强耐磨料中掺入任何添加剂,外掺料。
图1“L”钢筋钉载埋方法
6. 抹灰
待涂刷的界面剂表面指触干燥时,用抹刀将耐磨料抹在混凝土面层上,第一层抹灰时要用力按压。每次抹灰厚度不宜超过20mm,当耐磨层设计较厚时,待第一层抹灰层达到初凝状态后,进行下一层抹灰施工,施工至设计耐磨层厚度。
7. 压光
根据气候条件,1~2小时后,耐磨料接近初凝时进行压光处理。压光工序非常重要,可降低耐磨层表面的粗糙度,有利于出料通畅,不堵料。如果施工厚度较大,容易出现塑型裂纹,所以在第一次压光后1~2小时要进行第二次压光处理。
8. 养护
夏季施工,应在施工完毕后4小时内,高强抗磨料初凝后加盖湿草袋或岩棉被浇水养护。冬季施工,施工完毕后应立即覆盖塑料薄膜,并加盖草袋或岩棉被,并采取保温措施。养护期为7天,养护措施还应符合《钢筋混凝土工程施工及验收规范》中的有关规定。
洗选厂工程中精煤仓、原煤仓工程漏斗施工通过对基层处理、铺设钢筋网、涂刷界面剂、耐磨料搅拌、抹灰、压光,养护等方面施工,保证了抗磨层与混凝土基层的整体性,减少大面积抹灰造成的抗磨层收缩,增大约束,防止产生空鼓和裂纹,降低耐磨层表面的粗糙度,有利于出料通畅,不堵料,保证施工质量。
[文章编号]1619-2737(2012)08-24-207
[作者简介] 陈小敏,女,职称:助理工程师,工作单位:河南富昌建设工程有限责任公司。
【关键词】耐磨料基层;施工;养护
High-strength wear-resistant material construction program
Chen Xiao-min
(Henan Cheong Construction Engineering Co., LtdHebiHenan458000)
【Abstract】Henan Province Coal Group investment firm in coal washing plant engineering positions, coal storage hopper part of the project the construction of wear-resistant materials, wear-resistant layer of pre-construction, the original concrete base has hardened to achieve the ultimate strength, wear-resistant layer to ensure that the original concrete base and sticky connected firmly to form an organic whole, its wear-resistant construction materials, mainly from the grassroots, the laying of steel mesh, brushing interface, wear-resistant material mixing, plastering, calendar, maintenance, etc. to ensure the quality of construction to achieve the desired results.
【Key words】Wear-resistant material grassroots;Construction;Conservation
1. 概述
我单位所施工的河南煤化集团投资公司洗选厂工程中精煤仓、原煤仓工程漏斗部分耐磨料,首先在进行耐磨层施工前,对原有混凝土基层已施工完超过28天,达到最终硬化强度,保证耐磨层和原有混凝土基层粘接牢固,形成有机整体,采取以下三个必要的工艺准备:基层处理、铺设钢筋网、涂刷界面剂。
2. 基层处理
界面基層处理主要注意三点:(1)粗糙程度,基层越粗糙,界面结合面积越大,合力越大,抵抗剪切破坏的能力就越强,所以要对基层进行凿毛。(2)完好程度,指粘接面受损伤的程度,损伤越轻,内部产生缺陷越少,粘接性能越好,所以要对基础表面如有疏松部位应予剔除。(3)洁净程度,减少杂质,有利于提高粘接强度。所以要用压力水冲洗清理基础表面,不得有浮浆、浮灰和脱模剂等杂物。
3. 铺设钢筋网
为了保证抗磨层与混凝土基层的整体性,减少大面积抹灰造成的抗磨层收缩,增大约束,防止产生空鼓和裂纹,在基层表面需埋设钢筋网。
混凝土基层钻孔深50~70mm,孔径12mm;用MS-502钢筋锚固料锚固5~6mm钢筋钉,外露15~30mm(设计抗磨层厚度的1/3),钢筋钉之间的间距300mm,呈梅花形分布。或直接钻孔孔径6mm,孔深50mm,将钢筋钉直接砸入即可。
耐磨层厚度小于40mm时,只需载埋“L”钢筋钉即可进行下步施工。当耐磨层厚度不大于40mm时,在“L”钢筋钉的顶端需用5~6mm盘条焊接成网。
“L”钢筋钉载埋方法见图1。
4. 涂刷界面剂
4.1施工前2小时充分湿润基础表面,施工时将浮水吸干。
4.2将MS-702专用界面处理剂均匀涂刷在已处理好的混凝土基础表面,不能漏刷。
5. 耐磨料搅拌
耐磨料拌合时,加水量应按随货提供的产品合格证上的推存用水量加入,搅拌均匀,用水量可根据环境条件及实际工程情况适当调整,拌合用水应符合现行《混凝土拌合用水标准》的规定;
高强耐磨料可采用机械搅拌,建议采用强制式搅拌机进行机械搅拌,可以提高施工效率,搅拌时间一般为2~3分钟,保证搅拌充分均匀,施工效果更好。现场加水量为13%~14%加水搅拌,稠度以适合施工为宜,搅拌位置尽量靠近施工位置,以利施工的连续进行。从加水搅拌到施工完毕应控制在40分钟内为宜,因此应保证每次搅拌量与施工速度相匹配。
现场使用时,严禁在高强耐磨料中掺入任何添加剂,外掺料。
图1“L”钢筋钉载埋方法
6. 抹灰
待涂刷的界面剂表面指触干燥时,用抹刀将耐磨料抹在混凝土面层上,第一层抹灰时要用力按压。每次抹灰厚度不宜超过20mm,当耐磨层设计较厚时,待第一层抹灰层达到初凝状态后,进行下一层抹灰施工,施工至设计耐磨层厚度。
7. 压光
根据气候条件,1~2小时后,耐磨料接近初凝时进行压光处理。压光工序非常重要,可降低耐磨层表面的粗糙度,有利于出料通畅,不堵料。如果施工厚度较大,容易出现塑型裂纹,所以在第一次压光后1~2小时要进行第二次压光处理。
8. 养护
夏季施工,应在施工完毕后4小时内,高强抗磨料初凝后加盖湿草袋或岩棉被浇水养护。冬季施工,施工完毕后应立即覆盖塑料薄膜,并加盖草袋或岩棉被,并采取保温措施。养护期为7天,养护措施还应符合《钢筋混凝土工程施工及验收规范》中的有关规定。
洗选厂工程中精煤仓、原煤仓工程漏斗施工通过对基层处理、铺设钢筋网、涂刷界面剂、耐磨料搅拌、抹灰、压光,养护等方面施工,保证了抗磨层与混凝土基层的整体性,减少大面积抹灰造成的抗磨层收缩,增大约束,防止产生空鼓和裂纹,降低耐磨层表面的粗糙度,有利于出料通畅,不堵料,保证施工质量。