兰新铁路第二双线(新疆段)LXTJ9标段,DK1829+479红雁南路立交桥施工中,拆除中墩墩顶临时固结措施(也就是体系转换),使中墩永久支座受力,同时在边墩墩顶上灌筑边跨梁段(也就是8#段),安装边跨合拢段型钢支架,并对起实施临时锁定,用悬吊支架浇筑边跨合拢段,完成边跨合拢形成三跨连续梁。
During the construction of the LXTJ9 bidding section of the second lane (Xinjiang section) of LXTJ9 and the DK1829 + 479 Hongyin South Road overpass of the second double lane of Xinjiang-Xinjiang Railway, the temporary consolidation measures (that is, system conversion) At the same time in the piers pier pier at the edge of the beam section (that is, section 8 #), the installation of cross-section steel beam close section of the stent, and to implement a temporary lock, with the suspension bracket pouring side span closure section to complete the edge span closure Form a three-span continuous beam.