2006年6月29日以来,江苏省苏北地区连降暴雨,受强降雨影响,江苏省里下河、白马湖和宝应湖水位迅速上涨,苏北里下河地区涝情十分严峻。为确保涝区人民生命财产安全,南水北调江苏水源有限责任公司急灾区群众所急,想灾区群众所想,立即启动防汛预案,在江苏省防指的统一调度下,积极投入防汛排涝。按照江苏省防指紧急调度指令,2006年7月1日下午17时,南水北调宝应站首次投运参与里下河地区排涝。3日下午15时,开启备用机组,4台机组满负荷运行,最高排涝流量达到1 60 m3/s。至10日下午6时,机组连续运行10天共217小时,累计抽排涝水11乙m3,为有效缓解里下河地区汛情,促进地方经济发展发挥了重要作用,取得了抗灾斗争的阶段性胜利。
Since June 29, 2006, heavy rains continue to fall in northern Jiangsu Province. Due to the heavy rainfall, the water levels of Lixia River, Baima Lake and Baoying Lake in Jiangsu Province have rapidly risen. The flood control situation in the Lixiahe area in northern Jiangsu is very grim. In order to ensure the life and property safety of people in the flood-prone areas, the people in the disaster-stricken areas in the South-to-North Water Diversion Project of Jiangsu Water Resources Co., Ltd. are in urgent need of flood-hitter areas. They immediately started the flood control plan and actively put flood control and drainage measures under the unified control of Jiangsu defensive measures. In accordance with the Jiangsu Provincial Emergency Protection Dispatching Directive, at 17:00 on July 1, 2006, the Baoying Station of the South-to-North Water Diversion Project was put into operation for drainage drainage for the first time in the Lixiahe area. At 15:00 on the 3rd, open standby unit, 4 units at full capacity operation, the maximum drainage flow reached 1 60 m3 / s. At 6 pm on the 10th, the crew ran for 217 days in a row for 10 consecutive days, accumulating a total of 11 m 3 of drainage and drainage water, which played an important role in effectively alleviating the flood in the Lixiahe area and promoting local economic development, and achieved a phased victory in the fight against disasters .