论文部分内容阅读
本文对密苏里州Warsaw附近Harry S。Truman坝和水库的水电装置作了全面说明。该工程结合利用Ozarks湖作为其尾水池进行抽水蓄能。电站的六台机组,到目前为止是陆军工程团所安装的最大斜轴机组,而且是寻求经济低水头设计的尝试。抽水蓄能与斜轴技术相结合会出现某些特有的结构问题,文中对这些问题进行了详细的讨论。该装置目前处于建设和试验的最后阶段,本应于1980年完成。
This article addresses Harry S. near Warsaw, Missouri. Truman Dam and reservoir hydropower installation made a comprehensive description. The project combines the use of Lake Ozarks as its tailrace for pumped storage. The six units at the station are by far the largest inclined axis units installed by the Army Corps of Engineers and are an attempt to seek an economical low head design. Pumped storage and inclined axis technology will be some unique structural problems, the paper discussed in detail these issues. The installation is currently in the final stages of construction and testing and should have been completed in 1980.