以回弄山隧道施工过程中所遭遇的灾害性涌水突泥为例,分析研究了其形成原因和施工对策,得出了如下主要结论与建议:隧道施工中应综合多种地质手段以提高超前地质预报的准确性;涌水突泥有三种应对方案,即使对于同一隧道,也应根据地层条件、水量和水压、补给条件等因素合理选用;富水断层带及其影响带的施工应适当扩挖,并加强径向排水,或采用超前小导坑工法,二次衬砌宜紧跟。
Taking the disastrous gushing mud encountered in the construction of mountain tunnel as an example, the formation reason and construction countermeasure are analyzed and analyzed. The main conclusions and suggestions are as follows: In the tunnel construction, a variety of geological means should be integrated to improve the advance Geological forecast accuracy; gushing water mud has three coping schemes, even for the same tunnel, should be based on stratigraphic conditions, water and pressure, conditions of supply and other factors rational selection; the construction of the water-rich fault zone and its impact zone should be appropriate to expand Digging, and to strengthen the radial drainage, or the use of leading small pilot method, the secondary lining should be followed.