南水北调禹州长葛段工程膨胀岩渠坡换填改性土掺量试验,通过开展室内试验、现场碾压试验及试验后的成果总结,获得改性土处理措施的施工碾压参数、施工压实质量控制指标,为南水北调工程禹州长葛段膨胀岩渠坡改性土处理换填施工提供技术支持。
Through the tests carried out in the laboratory, the on-site rolling test and the summary of the results after the test, the construction roller compaction parameters of the modified soil treatment measures were obtained and the construction compaction Quality control indicators for the South-to-North Water Diversion Project of Yuzhou Chang Ge section of the slope to deal with the construction of landfill for technical support.