全国关注的大型、自动、现代化的宝山钢铁总厂,已于1985年9月15日起,从4063M~31~#高炉继而300T转炉至φ1300mm二架初轧机正式开工。在这以前,电厂、码头、原料场、焦化、烧结、石灰石和白云石焙烧以及水、气、运输、理化检验、通讯等配套项目早已运转。至此,宝钢I期工程的22个项目,除无缝钢管厂将于年底建成外,均已成功地投入热运转。并且运转得非常顺利,这是大快人心的事。开工尚不久现仅对宝钢投产的初步情况作一介绍。
The large-scale, automatic and modernized Baoshan Iron and Steel Plant, which is of concern to the whole country, started on September 15, 1985 with the start of 4060M ~ 31 # blast furnace and then 300T converter to φ1300mm two initial mill. Prior to this, supporting projects such as power plants, wharfs, raw material markets, coking, sintering, limestone and dolomite roasting, as well as water, gas, transportation, physical and chemical testing, and communications have long been running. So far, 22 projects of phase I of Baosteel have been successfully put into operation except for the completion of the seamless steel pipe plant by the end of this year. And it worked so well that it was a big blessing. It is not long ago to start an introduction on the initial situation of Baosteel’s commissioning.