针对成都地铁3号线6标出入段线盾构区间上穿熊猫大道站-天回镇南站区间右线隧道的工程背景,通过采用碗扣式脚手架对正线隧道进行加固,并对出入段线盾构掘进方案进行了合理设计。过正线掘进过程中对盾构机的掘进参数进行了监控,同时对成型隧道拱顶进行了沉降监测与分析。结果表明:盾构机在过正线掘进过程中始终保持匀速推进,且各项掘进参数均处于正常范围内;入线段拱顶沉降监测点RDX-232和RDX-252的累计沉降值为4.5 mm和3.3 mm,出线段拱顶沉降监测点CDX-604和CDX-624的累计沉降值为8.7 mm和3.3 mm,均处于可控状态。
According to the engineering background of the right-line tunnel on the 6th line of Chengdu Subway Line 3 and the shield zone of Panda Avenue Station - Tianhui Zhennan Station section, the frontal tunnel is reinforced by the bowl-button scaffold, Line shield tunneling program has been a reasonable design. During the tunneling process, the tunneling parameters of shield tunneling machine were monitored. At the same time, the settlement monitoring and analysis of the tunnel roof was carried out. The results show that the shield machine always keeps the same speed during the tunneling process, and all the driving parameters are within the normal range. The cumulative settlement of RDX-232 and RDX-252 at the vault settlement point is 4.5 mm And 3.3 mm respectively. The cumulative settlement values of CDX-604 and CDX-624 at the outlet settlement vault settlement point are 8.7 mm and 3.3 mm, both of which are in controllable state.