在佛开高速公路改扩建工程中,佛开高速公路仍处在原有业务不中断的状态。因此,佛开高速公路改扩建机电工程施工必然面临施工界面分散、不连续,以及新旧机电系统互相兼容、并存、切换的难点。如何在这些复杂的条件下完成机电项目工程施工,是对机电工程施工参建各方组织管理能力和工程实施资源合理应用的考验。文中重点论述了在佛开高速公路改扩建工程中的机电工程改扩建施工管理方面的有关经验。
In the Fokai Expressway expansion project, Fokai Expressway is still in the original state of business without interruption. Therefore, the reconstruction of Fokai Expressway construction of mechanical and electrical construction is bound to face scattered construction of the interface is not continuous, as well as the old and the new mechanical and electrical systems compatible, coexisting, the difficulty of switching. How to complete the construction of mechanical and electrical project under these complicated conditions is the test of reasonable utilization of the organizational management ability and engineering implementation resources of the participants in the construction of electromechanical engineering. The paper mainly discusses the relevant experience in the construction management of the mechatronics expansion project in the reconstruction and expansion of the Fokai Expressway.