1994年2月,我国引进外国资金、先进设备和技术建设的第一座大型核电站——广东大亚湾核电站一号机组正式投入商业运行。这是改革开放的产物,是建立现代企业的有益尝试。 大亚湾核电站是广东核电站投资有限公司合资兴建的大型核电站,装有两台从法国和英国引进的90万千瓦压水堆核电机组。1984年初开始动工,1990底各主要建筑物土建工程基本完成,今年2月1日,一号机组正式投入商业运行,二号机组可望在
In February 1994, China’s first large-scale nuclear power plant, Guangdong Daya Bay Nuclear Power Station, which was built with foreign capital, advanced equipment and technology, was formally put into commercial operation. This is a product of reform and opening up and is a useful attempt to establish a modern enterprise. Daya Bay Nuclear Power Station is a large-scale nuclear power plant jointly invested by Guangdong Nuclear Power Investment Co., Ltd. It is equipped with two 900,000 kilowatts PWR nuclear power units imported from France and the United Kingdom. Construction began in early 1984. The civil works for major buildings in the end of 1990 were basically completed. On February 1 this year, Unit 1 was officially put into commercial operation, and Unit 2 is expected to