工程施工优化的做法和体会山东电建三公司张科志我公司承建的潍坊电厂一号机组于1993年9月23日17时完成96小时连续试运转工作,顺利移交电厂。机组在试运转后移交,由于无缺陷可消,经试运指挥部决定,并向省局汇报,机组试运96小时后继续不停运行。从机组的...
Optimization of Engineering Construction and Experiences The first unit of Weifang Power Plant, which was built by Zhang Kezhi, our company, completed the 96-hour continuous test run at 17 o’clock on September 23, 1993, and was successfully transferred to the power plant. The unit is handed over after the trial operation. As no defects can be eliminated, it is decided by the trial transport headquarters and reported to the provincial bureau. The unit will continue to operate after 96 hours of trial operation. From the unit...