摘要:随着光纤通信技术的快速发展,光缆施工技术和难度也日益复杂,正确把握光缆施工技术及提高施工质量是确保光缆线路安全和优质传输的关键。本文从施工准备、路由复测、挖填光缆沟、光缆敷设、光缆接续等方面探讨了光缆线路工程的施工技术,并总结了光缆线路工程施工质量控制措施和注意事项,旨在提高光缆线路工程施工质量。
关键词:直埋光缆;线路;路由复测;敷设;接续;质量控制
Abstract: with the rapid development of the optical fiber communication technology, fiber optic cable construction technology and difficulty also increasingly complex, grasping the fiber optic cable construction technology and improve the construction quality is to ensure safety and high quality transmission fiber optic cable line of the key. This paper, from the construction preparation, routing reeated measure, dig fill in the optical cable, optical cable, optical cable laying ditch succeeded, and discussed the fiber optic cable line construction technology, and sums up the fiber optic cable line engineering construction quality control measures and attention, to improve the fiber optic cable line engineering construction quality.
Keywords: buried cable; Line; Routing reeated measure; For laying; In; Quality control
近年來,光纤通信技术发展迅速,具有通信容量大、传输距离长、传输质量好、保密性能佳的优点,以其独特的优越性成为当今信息传输的重要手段。光缆作为信号与数据传输的载体,它的正确敷设是发挥光纤作用的前提和保证。一般而言,光缆敷设分为4种方式:直埋光缆敷设、管道光缆敷设、架空光缆敷设和水底光缆敷设。其中直埋光缆敷设中的应用最普遍。本文就以直埋光缆线路工程为例,谈谈光缆线路的施工。
1 施工准备
(1)组建一只高素质的施工队伍。这一点至关重要,因为光缆施工比电缆施工要求严格的多,任何施工中的疏忽都将可能造成光钎损耗增大,甚至断芯;
(2)设立临时设施,临时设施包括项目经理办公室、材料及仪表设备的存放地、宿舍、食堂设施的建立,安全设施及防火、防水设施的设置,保安防护设施的设立。设立临时设施的原则时:距离施工现场就近;运输材料、设备、机具便利;通信、信息传递方便人身及物资安全;
(3)进行必要的材料厂验,签订材料的供货合同,及时采购承包的主要材料及计划内的辅助材料、劳保用品,做好材料及设备的清点、进场检验及标识工作,并对其数量、规格等进行等级,建立台帐。材料和设备进场检验工作应有建设单位随工人员和监理人员在场,并由随工人员和监理人员确认,将检验记录备案;
(4)清点施工机具、仪表和工具,并建立台帐;
(5)安装调试施工机具、设备、仪表,做好施工机具和施工设备的安装、调试工作,避免施工时设备和机具发生故障,造成窝工,影响施工进度。
2 直埋光缆线路路由复测
2.1 直埋光缆线路路由复测的主要任务
直埋光缆线路路由复测的主要任务包括:根据设计核定光缆的路由走向、敷设位置、环境条件及配套设施的安装地点;核定和测量各种敷设地面距离,核定光缆穿越铁路、公路、河流、湖泊及大型水库、地下管线以及其他障碍物的具体位置及技术措施;核定三防地段的长度、措施及实施的可能性;核定沟坎保护的地点和数量;根据环境条件,初步确定接头位置;为光缆的配盘、分屯及敷设提供必要的数据资料;修改、补充施工图纸;
2.2 路由复测的原则
复测时应严格按照批准的施工图设计进行,如遇特殊情况或由于现场条件发生变化等其他原因,必须变更施工图设计选定的路由方案或需要进行较大范围变动时,应与设计、建设单位协商确定,并按建设程序办理变更手续;市区内光缆敷设路由及在规划线内穿越公路、铁路位置如发生变化时,应报当地相关部门审批后确定。光缆线路路由与其他建筑设施间的间距应符合《通信线路工程验收规范》规定;
2.3 路由复测的工作内容
路由复测小组由施工单位组织,小组成员由施工、监理、建设(或维护)和设计单位的人员组成。施工过程中完成定线、测距、打标线、划线、绘图、等工作。
绘图时应核实复测的路由与设计施工图有无差异,路由变动部分应按照施工图的比例绘出路由位置及路由两侧50米以内的地形和主要建筑物;绘出“三防”设施的位置和保护措施、具体长度等。穿越较大障碍物时,如位置变更应测绘出新的断面图。
3 光缆的单盘检验与配盘
光缆检验应在光缆运达现场,分屯点后进行。主要进行外观检查和光特性测试。
外观检查:检查光缆盘有无变形,护板有无损伤,各种随盘资料是否齐全。外观检查工作应请供应单位一起进行。开盘后应先检查光缆外表有无损伤;对经过检验的光缆应做记录,并在缆盘上做好标识。
光缆的光电性能检验:包括光缆长度的复测、光缆单盘损耗测量、光纤向后散射信号曲线观察和光缆护层的绝缘检查等内容。
4 挖填光缆沟
(1)直埋光缆与其他建筑设施间的最小间距应满足设计要求或验收规范规定;
(2)光缆沟的截面尺寸应符合施工设计图要求,其沟底宽度随光缆数目而变;
(3)光缆埋深应符合设计要求;
(4)光缆沟的质量要求为五个字:直、弧、深、平、宽。即以施工单位所画灰线为中心开挖缆沟,光缆线路直线段要直,不得出现蛇形弯;转角点应为圆形弧,不得出现锐角;按土质及地段状况,缆沟应达到设计规定深度;沟底要平坦,不能出现局部梗阻、塌方或深度不够问题;为了保证附属设施的安装质量,必须按标准保证沟底的宽带。
(5)光缆缆沟回填土时,应先回填300mm厚的碎土或细土,并应人工踏平。石质沟应在敷设前、后铺100mm厚碎土或细土;待安装完其他配套设施后,再继续回填土,每回填300mm应人工踏平一次;第一次回填时,严禁用铁锨、镐等锐利工具接触光缆,以免损伤光缆;回填土应高出地面100mm。
5 光缆敷设安装及保护
(1)同沟敷设的光缆不得重叠或交叉,缆间的平行距离应不小于100mm;布放光缆时应防止光缆在地上拖放,特别是丘陵、山区、石质地带,应采取措施防止光缆外护层摩擦破损;保证光缆全部贴到沟底,不得有背扣;光缆在各类管材中穿放时,管材内经应不小于光缆外径的1.5倍;
(2)穿越允许开外路面的公路或乡村大道时,光缆应采用钢管或塑料管保护;穿越有动土可能的机耕路时,应采用红砖或水泥盖板保护;通过村镇等动土可能较大的地段时,可采用大长塑料管、铺红砖或水泥盖板保护;穿越有疏浚、拓宽规划或挖泥可能的沟渠、水塘时,可采用半硬塑料管保护,并在上方覆盖水泥盖板或水泥砂浆袋。
6 光缆的敷设
光缆敷设时,应按照A、B端敷设;在光缆布放时严禁光缆打小圈、折、扭曲,并要配一定数量的对讲机,“前走后跟,光缆上肩”的方法,能够有效的防止背扣的发生,还要注意用力均匀,牵引力不超过光缆允许的80%,瞬间最大牵引力不超过100%。另外,架设时,在光缆转弯处或地形较复杂处应有专人负责,严禁车辆碾压。
7 光缆线路标石的埋设
(1)埋设光缆标石地点:光缆接头处、转弯处、预留处;直埋光缆的接头处应设置检测标石;穿越障碍物或直线段落较长,利用前后两个标石或其他参照物寻找光缆有困难的地方;敷设防雷线、同沟敷设光缆起止地点;需要埋设标石的其他地点。可以利用固定的标志来标识光缆的位置时,可不埋设标石。
(2)标石埋设应符合规范要求;
8 光缆线路对地绝缘
(1)直埋光缆线路对地绝缘测试,应在光缆回填300mm后和光缆接头盒封装回填后进行。光缆线路对地绝缘监测装置应与光缆的金属护层、金属加强芯及接头盒进水检测电极相连接。
(2)直埋光缆线路对地绝缘电阻测试,应根据被测试对地绝缘电阻值的范围,按仪表量程确定使用高阻计或兆欧表。
(3)绝缘电阻的测试,应避免在相对湿度大于80%的条件下进行;
(4)测试仪表引线的绝缘强度应满足测试要求,且长度不得超过2m;
(5)对地绝缘监测装置的连接方式应符合设计要求;
(6)埋设后的单盘直埋光缆,金属外护层对地绝缘电阻的竣工验收指标应不低于10MΩ.Km,其中10%的单盘光缆应不低于2MΩ。
9 光缆的接续、测试
9.1 光缆的接续
①光缆接续的内容包括:光缆接续、金属护层和加强芯的处理、接头护套的密封及监测线的安装。光缆接续的一般要求为:光纤接续前应核对光缆端别、光纤纤序,并对端别及光纤纤序作识别标志。固定接头光纤接续应采用熔接法,活动接头光纤连接应采用成品光纤连接器。
②光纤接续时,现场采用OTDR监测连接质量,并及时做好光纤接续损耗和光纤长度记录。光纤接头损耗应到达设计规定值。直埋光缆接续前后应测量光缆金属护层的对地绝缘电阻,以确認单盘光缆的外护层是否完好和接头盒安装密封是否良好;光缆加强芯在接头盒内应固定牢固,金属构件在接头处一般应电气断开。
9.2 光缆测试
①在实际工作中,光纤连接损耗的现场监测普遍采用OTDR监测法。该方法在精确测量接头损耗的同时,还能测试光纤单位长度的损耗和光纤的长度,观测被接光纤是否出现损伤和断纤。在工程中应推广使用远端环回监测法,光纤接头损耗的评价以该接头的双向测试的算术平均值为准。
②光缆中继段测试内容包括中继段光纤线路衰减系数及传输长度、光纤通道总衰减、光纤后向散射信号曲线、偏振模色散(PMD)和光缆对地绝缘。
10 直埋光缆施工的建议
(1)光缆布放前,应对施工及相关人员就施工应注意的事项进行适当的培训,如放线方法要领和安全等内容,并确保施工人员服从指挥;
(2)由于爬坡直埋光缆较重,且布放地形复杂,因此施工比较困难,所需人工较多;建议在施工爬坡光缆时,应配备足够人员(建议130人左右);
(3)光缆布放时,工程队技术人员应配备必要的通讯设备,如对讲机等;技术人员应分布在光缆盘“8”处、穿越障碍点、地形拐弯处和光缆前端引导等处,控制光缆布放速度避免出现“浪涌”现象或在光缆中间出现积留时急拉造成打“背扣”的现象;
(4)光缆穿过PVC管时,应指导放缆人员将光缆直穿进PVC管,避免出现光缆扭曲。以避免光缆在放出一段距离后,在PVC管附近积成小圈,进而继续拉直光缆,造成光缆严重扭曲;
(5)打“8”字时,应选择合适的地形,将“8”字尽量打大,为避免解“8”字时产生问题,应在情况允许的前提下,尽量少打“8”字;
(6)解“8”字时应正确操作,将“8”字逆着打“8”字的方向解开;若出现“8”字翻转不当,造成“8”字将解尽时仍有应力产生的小圈不能解开,切勿将小圈拉直,应在小圈积留处做预留处理;
(7)回土之前应由工程技术人员将光缆理顺,使其成自然平直状态,避免在光线未理顺时回土。
11 结束语
总之,光纤通信目前已广泛应用于国民经济建设当中,光缆线路工程是实现光纤通信的重要组成部分。而光缆线路工程的施工是一门技术很强的工作,施工质量的好坏是光纤通信的前提和保证。
参考文献
[1] 潘圣,光缆线路施工中的常见问题及解决办法[J].信息通信,2012.04
[2] 孙泰福,光缆线路维护与管理[J].现代情报,2006.09
文献标识码: A 文章编号:
摘要:随着光纤通信技术的快速发展,光缆施工技术和难度也日益复杂,正确把握光缆施工技术及提高施工质量是确保光缆线路安全和优质传输的关键。本文从施工准备、路由复测、挖填光缆沟、光缆敷设、光缆接续等方面探讨了光缆线路工程的施工技术,并总结了光缆线路工程施工质量控制措施和注意事项,旨在提高光缆线路工程施工质量。
关键词:直埋光缆;线路;路由复测;敷设;接续;质量控制
Abstract: with the rapid development of the optical fiber communication technology, fiber optic cable construction technology and difficulty also increasingly complex, grasping the fiber optic cable construction technology and improve the construction quality is to ensure safety and high quality transmission fiber optic cable line of the key. This paper, from the construction preparation, routing reeated measure, dig fill in the optical cable, optical cable, optical cable laying ditch succeeded, and discussed the fiber optic cable line construction technology, and sums up the fiber optic cable line engineering construction quality control measures and attention, to improve the fiber optic cable line engineering construction quality.
Keywords: buried cable; Line; Routing reeated measure; For laying; In; Quality control
近年來,光纤通信技术发展迅速,具有通信容量大、传输距离长、传输质量好、保密性能佳的优点,以其独特的优越性成为当今信息传输的重要手段。光缆作为信号与数据传输的载体,它的正确敷设是发挥光纤作用的前提和保证。一般而言,光缆敷设分为4种方式:直埋光缆敷设、管道光缆敷设、架空光缆敷设和水底光缆敷设。其中直埋光缆敷设中的应用最普遍。本文就以直埋光缆线路工程为例,谈谈光缆线路的施工。
1 施工准备
(1)组建一只高素质的施工队伍。这一点至关重要,因为光缆施工比电缆施工要求严格的多,任何施工中的疏忽都将可能造成光钎损耗增大,甚至断芯;
(2)设立临时设施,临时设施包括项目经理办公室、材料及仪表设备的存放地、宿舍、食堂设施的建立,安全设施及防火、防水设施的设置,保安防护设施的设立。设立临时设施的原则时:距离施工现场就近;运输材料、设备、机具便利;通信、信息传递方便人身及物资安全;
(3)进行必要的材料厂验,签订材料的供货合同,及时采购承包的主要材料及计划内的辅助材料、劳保用品,做好材料及设备的清点、进场检验及标识工作,并对其数量、规格等进行等级,建立台帐。材料和设备进场检验工作应有建设单位随工人员和监理人员在场,并由随工人员和监理人员确认,将检验记录备案;
(4)清点施工机具、仪表和工具,并建立台帐;
(5)安装调试施工机具、设备、仪表,做好施工机具和施工设备的安装、调试工作,避免施工时设备和机具发生故障,造成窝工,影响施工进度。
2 直埋光缆线路路由复测
2.1 直埋光缆线路路由复测的主要任务
直埋光缆线路路由复测的主要任务包括:根据设计核定光缆的路由走向、敷设位置、环境条件及配套设施的安装地点;核定和测量各种敷设地面距离,核定光缆穿越铁路、公路、河流、湖泊及大型水库、地下管线以及其他障碍物的具体位置及技术措施;核定三防地段的长度、措施及实施的可能性;核定沟坎保护的地点和数量;根据环境条件,初步确定接头位置;为光缆的配盘、分屯及敷设提供必要的数据资料;修改、补充施工图纸;
2.2 路由复测的原则
复测时应严格按照批准的施工图设计进行,如遇特殊情况或由于现场条件发生变化等其他原因,必须变更施工图设计选定的路由方案或需要进行较大范围变动时,应与设计、建设单位协商确定,并按建设程序办理变更手续;市区内光缆敷设路由及在规划线内穿越公路、铁路位置如发生变化时,应报当地相关部门审批后确定。光缆线路路由与其他建筑设施间的间距应符合《通信线路工程验收规范》规定;
2.3 路由复测的工作内容
路由复测小组由施工单位组织,小组成员由施工、监理、建设(或维护)和设计单位的人员组成。施工过程中完成定线、测距、打标线、划线、绘图、等工作。
绘图时应核实复测的路由与设计施工图有无差异,路由变动部分应按照施工图的比例绘出路由位置及路由两侧50米以内的地形和主要建筑物;绘出“三防”设施的位置和保护措施、具体长度等。穿越较大障碍物时,如位置变更应测绘出新的断面图。
3 光缆的单盘检验与配盘
光缆检验应在光缆运达现场,分屯点后进行。主要进行外观检查和光特性测试。
外观检查:检查光缆盘有无变形,护板有无损伤,各种随盘资料是否齐全。外观检查工作应请供应单位一起进行。开盘后应先检查光缆外表有无损伤;对经过检验的光缆应做记录,并在缆盘上做好标识。
光缆的光电性能检验:包括光缆长度的复测、光缆单盘损耗测量、光纤向后散射信号曲线观察和光缆护层的绝缘检查等内容。
4 挖填光缆沟
(1)直埋光缆与其他建筑设施间的最小间距应满足设计要求或验收规范规定;
(2)光缆沟的截面尺寸应符合施工设计图要求,其沟底宽度随光缆数目而变;
(3)光缆埋深应符合设计要求;
(4)光缆沟的质量要求为五个字:直、弧、深、平、宽。即以施工单位所画灰线为中心开挖缆沟,光缆线路直线段要直,不得出现蛇形弯;转角点应为圆形弧,不得出现锐角;按土质及地段状况,缆沟应达到设计规定深度;沟底要平坦,不能出现局部梗阻、塌方或深度不够问题;为了保证附属设施的安装质量,必须按标准保证沟底的宽带。
(5)光缆缆沟回填土时,应先回填300mm厚的碎土或细土,并应人工踏平。石质沟应在敷设前、后铺100mm厚碎土或细土;待安装完其他配套设施后,再继续回填土,每回填300mm应人工踏平一次;第一次回填时,严禁用铁锨、镐等锐利工具接触光缆,以免损伤光缆;回填土应高出地面100mm。
5 光缆敷设安装及保护
(1)同沟敷设的光缆不得重叠或交叉,缆间的平行距离应不小于100mm;布放光缆时应防止光缆在地上拖放,特别是丘陵、山区、石质地带,应采取措施防止光缆外护层摩擦破损;保证光缆全部贴到沟底,不得有背扣;光缆在各类管材中穿放时,管材内经应不小于光缆外径的1.5倍;
(2)穿越允许开外路面的公路或乡村大道时,光缆应采用钢管或塑料管保护;穿越有动土可能的机耕路时,应采用红砖或水泥盖板保护;通过村镇等动土可能较大的地段时,可采用大长塑料管、铺红砖或水泥盖板保护;穿越有疏浚、拓宽规划或挖泥可能的沟渠、水塘时,可采用半硬塑料管保护,并在上方覆盖水泥盖板或水泥砂浆袋。
6 光缆的敷设
光缆敷设时,应按照A、B端敷设;在光缆布放时严禁光缆打小圈、折、扭曲,并要配一定数量的对讲机,“前走后跟,光缆上肩”的方法,能够有效的防止背扣的发生,还要注意用力均匀,牵引力不超过光缆允许的80%,瞬间最大牵引力不超过100%。另外,架设时,在光缆转弯处或地形较复杂处应有专人负责,严禁车辆碾压。
7 光缆线路标石的埋设
(1)埋设光缆标石地点:光缆接头处、转弯处、预留处;直埋光缆的接头处应设置检测标石;穿越障碍物或直线段落较长,利用前后两个标石或其他参照物寻找光缆有困难的地方;敷设防雷线、同沟敷设光缆起止地点;需要埋设标石的其他地点。可以利用固定的标志来标识光缆的位置时,可不埋设标石。
(2)标石埋设应符合规范要求;
8 光缆线路对地绝缘
(1)直埋光缆线路对地绝缘测试,应在光缆回填300mm后和光缆接头盒封装回填后进行。光缆线路对地绝缘监测装置应与光缆的金属护层、金属加强芯及接头盒进水检测电极相连接。
(2)直埋光缆线路对地绝缘电阻测试,应根据被测试对地绝缘电阻值的范围,按仪表量程确定使用高阻计或兆欧表。
(3)绝缘电阻的测试,应避免在相对湿度大于80%的条件下进行;
(4)测试仪表引线的绝缘强度应满足测试要求,且长度不得超过2m;
(5)对地绝缘监测装置的连接方式应符合设计要求;
(6)埋设后的单盘直埋光缆,金属外护层对地绝缘电阻的竣工验收指标应不低于10MΩ.Km,其中10%的单盘光缆应不低于2MΩ。
9 光缆的接续、测试
9.1 光缆的接续
①光缆接续的内容包括:光缆接续、金属护层和加强芯的处理、接头护套的密封及监测线的安装。光缆接续的一般要求为:光纤接续前应核对光缆端别、光纤纤序,并对端别及光纤纤序作识别标志。固定接头光纤接续应采用熔接法,活动接头光纤连接应采用成品光纤连接器。
②光纤接续时,现场采用OTDR监测连接质量,并及时做好光纤接续损耗和光纤长度记录。光纤接头损耗应到达设计规定值。直埋光缆接续前后应测量光缆金属护层的对地绝缘电阻,以确認单盘光缆的外护层是否完好和接头盒安装密封是否良好;光缆加强芯在接头盒内应固定牢固,金属构件在接头处一般应电气断开。
9.2 光缆测试
①在实际工作中,光纤连接损耗的现场监测普遍采用OTDR监测法。该方法在精确测量接头损耗的同时,还能测试光纤单位长度的损耗和光纤的长度,观测被接光纤是否出现损伤和断纤。在工程中应推广使用远端环回监测法,光纤接头损耗的评价以该接头的双向测试的算术平均值为准。
②光缆中继段测试内容包括中继段光纤线路衰减系数及传输长度、光纤通道总衰减、光纤后向散射信号曲线、偏振模色散(PMD)和光缆对地绝缘。
10 直埋光缆施工的建议
(1)光缆布放前,应对施工及相关人员就施工应注意的事项进行适当的培训,如放线方法要领和安全等内容,并确保施工人员服从指挥;
(2)由于爬坡直埋光缆较重,且布放地形复杂,因此施工比较困难,所需人工较多;建议在施工爬坡光缆时,应配备足够人员(建议130人左右);
(3)光缆布放时,工程队技术人员应配备必要的通讯设备,如对讲机等;技术人员应分布在光缆盘“8”处、穿越障碍点、地形拐弯处和光缆前端引导等处,控制光缆布放速度避免出现“浪涌”现象或在光缆中间出现积留时急拉造成打“背扣”的现象;
(4)光缆穿过PVC管时,应指导放缆人员将光缆直穿进PVC管,避免出现光缆扭曲。以避免光缆在放出一段距离后,在PVC管附近积成小圈,进而继续拉直光缆,造成光缆严重扭曲;
(5)打“8”字时,应选择合适的地形,将“8”字尽量打大,为避免解“8”字时产生问题,应在情况允许的前提下,尽量少打“8”字;
(6)解“8”字时应正确操作,将“8”字逆着打“8”字的方向解开;若出现“8”字翻转不当,造成“8”字将解尽时仍有应力产生的小圈不能解开,切勿将小圈拉直,应在小圈积留处做预留处理;
(7)回土之前应由工程技术人员将光缆理顺,使其成自然平直状态,避免在光线未理顺时回土。
11 结束语
总之,光纤通信目前已广泛应用于国民经济建设当中,光缆线路工程是实现光纤通信的重要组成部分。而光缆线路工程的施工是一门技术很强的工作,施工质量的好坏是光纤通信的前提和保证。