【摘要】渠道伸缩缝填料及其施工工艺,是渠道防渗中必须解决的问题。实际工程中,对渠道已铺衬土工膜的,以求节省费用,对铺衬土工膜,有的采用沥青砂浆、焦油朔料胶泥进行灌缝处理。这种材料受气温影响,温度高表面壅起,温度低脆裂,易老化且不环保;由于裂缝易导致渠道渗透破坏,需尝试采用新的材料和新的施工方法进行防渗。
【关键词】渠道伸缩缝;聚氨酯砂浆;防渗
【Abstract】The channel expansion joint filler and its construction technology, is to be anti-seepage problems. The actual project, on the channels Shop geomembrane liner in order to save costs, on the Shop geomembrane liner, and some use of asphalt mortar, tar plastics processing clay for irrigation joints. This material affected by the temperature, the temperature high surface obstruct, the temperature low rattle, aging is not easy to environmental protection; as a result of the cracks easily lead to the infiltration and sabotage channels need to try new materials and new construction methods for anti-seepage.
【Key words】Channel expansion joints;Polyurethane mortar;Seepage
1. 工程概况
(1)某工程渠线全长168.8Km,属大(Ⅰ)型Ⅰ等工程,工程主要由渠首分水枢纽、输水明渠、无压输水隧洞,分水闸、节制退水闸,输水渡槽,排洪渡槽,排洪涵洞,交通桥等建筑物组成。
(2)根据该工程设计结构,渠道长19.955m为一个隔梁段,一个隔梁段有四道垂直渠道断面的伸缩缝,伸缩缝长度沿隔梁边和渠道衬砌板边布置,伸缩缝的宽度为20mm,缝深60mm;干渠伸缩缝所采用的灌注材料按重量比4:6现场拌制的聚胺脂砂浆;在防渗渠道是梯形断面的情况下,聚氨酯砂浆灌注渠坡缝内使其达到设计要求,也不是一件容易的事;根据伸缩缝的断面结构,气温条件下,水平缝聚氨酯砂浆选用自流型,斜坡缝聚氨酯砂浆选用非下垂型。
2. 伸缩缝处理的几种型式
2.1沥青砂浆填缝。
填缝材料采用1:1:4(沥青:水泥:砂)沥青砂浆,施工时先将沥青加热至140~170℃,水泥和砂分别加热至160℃,将沥青、水泥和砂按比例装入容器内搅拌均匀,至颜色一致。在灌注沥青砂浆前先将伸缩缝内清理干净,灌注温度不低于110℃,待温度降低后用勾缝刀压实抹光。该法在经济投入上相对较省,但材料不环保,夏季高温施工时易流淌,受温度影响易老化。
2.2焦油塑料胶泥填缝。
焦油朔料胶泥配比按煤焦油:聚氯乙烯薄膜:癸二酸二辛酯 :粉煤灰=100:15:2:30配制。该法在经济投入上最省,采用废旧朔膜作为填料熬制,材料杂质较多,随坡流淌,渠坡灌缝困难,夏季胶泥表面易壅起,冬季易脆裂。
2.3聚氨酯砂浆填缝。
聚氨酯砂浆作为新型的材料,用于伸缩缝灌缝材料,施工简便,课低温操作,高温不流淌,低温不脆裂,-3 ℃有较好的弹性,无毒无害,耐老化性能好,在实际施工中经试验后效果很好,但原材料价格较高。
3. 双组份聚氨酯砂浆灌缝施工方法
为了使的材料防渗性能得到充分发挥,同时使工程经济投入投入得到有效的节省,设计经过各种方案的比选并结合新疆水利工程施工多年经验,以及新疆地区夏季干燥、炎热,冬季寒冷的特点,对明渠伸缩缝采用双组分聚氨酯砂浆灌缝处理。
3.1伸缩缝施工方法(伸缩缝采用的施工方法见表1)。
3.2伸缩缝施工注意事项。
(1)采用小灰铲或铁钩,将伸缩缝内、缝壁的砂石、泥土、杂物等附着物剔除,再采用扫帚进行清扫,再采用空压机等其它机械吹去灰尘,保证缝内清理后应无杂物、浮土,缝壁应清洁干燥。
(2)根据设计要求,在施工现场根据每个隔梁段所需要的聚氨酯砂浆具体方量,人工进行配置聚氨脂砂浆,比例按聚氨脂砂浆配比:酯:砂=4:6(重量比),聚氨酯砂浆所要求的砂料为水洗干燥砂,严格加强聚氨脂与砂料比例计量,拌合均匀。
(3)将配制好的聚氨酯砂浆装入开口方盘内,进行水平缝灌缝,在整个灌缝过程中,要防止杂物及土块落入缝中;下垂缝放置30分钟左右再灌缝,防止流淌过快。
(4)灌入的聚氨酯砂浆应密室,不得有断头或空洞,配合灌注工序,用勾缝刀封堵缝口,使聚氨酯砂浆不溢出缝外,最后修整表面,保持缝面平整。
(5)被灌入的聚氨酯砂浆应填筑至预制板板面一下1cm。
(6)聚氨脂砂浆填缝施工后8小时内防止与水接触,雾天、雨天应停止施工(A、B组份聚氨酯拌合见图1、聚氨酯与砂拌合见图2)。
4. 结束语
聚氨酯砂浆是由聚氨酯和水洗干砂按一定比例配制的一种材料,累似于嵌缝油膏,材料环保、填充粘结力强,变形性能大,且在当地最高气温下不流淌,最低气温下仍具有柔性,在满足伸缩缝填缝材料使用功能的前提下,聚氨酯砂浆具有常温作业、施工工艺简单,工程造价较高,性能优良,具有常温作业特点,24小时可固化,6~7天达到最大粘接强度;近年来,聚氨酯作为止水材料目前国内广泛使用,聚氨酯砂浆通过在新疆引额济克、引额济乌及南疆地区等大型水利工程应用检验证明,各标段施工现场集中拌合管理,灌缝质量完全满足设计要求,聚氨酯砂浆的止水效果良好。
参考文献
[1]《渠道防渗工程技术规范》SL18-91.2004.
[2]张立德.沙漠明渠工程设计施工关键技术研究与实践.中国水利水电.2007.
【关键词】渠道伸缩缝;聚氨酯砂浆;防渗
【Abstract】The channel expansion joint filler and its construction technology, is to be anti-seepage problems. The actual project, on the channels Shop geomembrane liner in order to save costs, on the Shop geomembrane liner, and some use of asphalt mortar, tar plastics processing clay for irrigation joints. This material affected by the temperature, the temperature high surface obstruct, the temperature low rattle, aging is not easy to environmental protection; as a result of the cracks easily lead to the infiltration and sabotage channels need to try new materials and new construction methods for anti-seepage.
【Key words】Channel expansion joints;Polyurethane mortar;Seepage
1. 工程概况
(1)某工程渠线全长168.8Km,属大(Ⅰ)型Ⅰ等工程,工程主要由渠首分水枢纽、输水明渠、无压输水隧洞,分水闸、节制退水闸,输水渡槽,排洪渡槽,排洪涵洞,交通桥等建筑物组成。
(2)根据该工程设计结构,渠道长19.955m为一个隔梁段,一个隔梁段有四道垂直渠道断面的伸缩缝,伸缩缝长度沿隔梁边和渠道衬砌板边布置,伸缩缝的宽度为20mm,缝深60mm;干渠伸缩缝所采用的灌注材料按重量比4:6现场拌制的聚胺脂砂浆;在防渗渠道是梯形断面的情况下,聚氨酯砂浆灌注渠坡缝内使其达到设计要求,也不是一件容易的事;根据伸缩缝的断面结构,气温条件下,水平缝聚氨酯砂浆选用自流型,斜坡缝聚氨酯砂浆选用非下垂型。
2. 伸缩缝处理的几种型式
2.1沥青砂浆填缝。
填缝材料采用1:1:4(沥青:水泥:砂)沥青砂浆,施工时先将沥青加热至140~170℃,水泥和砂分别加热至160℃,将沥青、水泥和砂按比例装入容器内搅拌均匀,至颜色一致。在灌注沥青砂浆前先将伸缩缝内清理干净,灌注温度不低于110℃,待温度降低后用勾缝刀压实抹光。该法在经济投入上相对较省,但材料不环保,夏季高温施工时易流淌,受温度影响易老化。
2.2焦油塑料胶泥填缝。
焦油朔料胶泥配比按煤焦油:聚氯乙烯薄膜:癸二酸二辛酯 :粉煤灰=100:15:2:30配制。该法在经济投入上最省,采用废旧朔膜作为填料熬制,材料杂质较多,随坡流淌,渠坡灌缝困难,夏季胶泥表面易壅起,冬季易脆裂。
2.3聚氨酯砂浆填缝。
聚氨酯砂浆作为新型的材料,用于伸缩缝灌缝材料,施工简便,课低温操作,高温不流淌,低温不脆裂,-3 ℃有较好的弹性,无毒无害,耐老化性能好,在实际施工中经试验后效果很好,但原材料价格较高。
3. 双组份聚氨酯砂浆灌缝施工方法
为了使的材料防渗性能得到充分发挥,同时使工程经济投入投入得到有效的节省,设计经过各种方案的比选并结合新疆水利工程施工多年经验,以及新疆地区夏季干燥、炎热,冬季寒冷的特点,对明渠伸缩缝采用双组分聚氨酯砂浆灌缝处理。
3.1伸缩缝施工方法(伸缩缝采用的施工方法见表1)。
3.2伸缩缝施工注意事项。
(1)采用小灰铲或铁钩,将伸缩缝内、缝壁的砂石、泥土、杂物等附着物剔除,再采用扫帚进行清扫,再采用空压机等其它机械吹去灰尘,保证缝内清理后应无杂物、浮土,缝壁应清洁干燥。
(2)根据设计要求,在施工现场根据每个隔梁段所需要的聚氨酯砂浆具体方量,人工进行配置聚氨脂砂浆,比例按聚氨脂砂浆配比:酯:砂=4:6(重量比),聚氨酯砂浆所要求的砂料为水洗干燥砂,严格加强聚氨脂与砂料比例计量,拌合均匀。
(3)将配制好的聚氨酯砂浆装入开口方盘内,进行水平缝灌缝,在整个灌缝过程中,要防止杂物及土块落入缝中;下垂缝放置30分钟左右再灌缝,防止流淌过快。
(4)灌入的聚氨酯砂浆应密室,不得有断头或空洞,配合灌注工序,用勾缝刀封堵缝口,使聚氨酯砂浆不溢出缝外,最后修整表面,保持缝面平整。
(5)被灌入的聚氨酯砂浆应填筑至预制板板面一下1cm。
(6)聚氨脂砂浆填缝施工后8小时内防止与水接触,雾天、雨天应停止施工(A、B组份聚氨酯拌合见图1、聚氨酯与砂拌合见图2)。
4. 结束语
聚氨酯砂浆是由聚氨酯和水洗干砂按一定比例配制的一种材料,累似于嵌缝油膏,材料环保、填充粘结力强,变形性能大,且在当地最高气温下不流淌,最低气温下仍具有柔性,在满足伸缩缝填缝材料使用功能的前提下,聚氨酯砂浆具有常温作业、施工工艺简单,工程造价较高,性能优良,具有常温作业特点,24小时可固化,6~7天达到最大粘接强度;近年来,聚氨酯作为止水材料目前国内广泛使用,聚氨酯砂浆通过在新疆引额济克、引额济乌及南疆地区等大型水利工程应用检验证明,各标段施工现场集中拌合管理,灌缝质量完全满足设计要求,聚氨酯砂浆的止水效果良好。