呼伦贝尔油田区块分散、单井产能低,地面系统按照常规的工艺规划设计百万吨产能地面建设投资达到20.9亿元。为降低地面建设投资,提高油田开发效益,2008年贝尔油田规模开发建设开始采用电加热管+油气混输油气集输工艺,简化地面集油流程、优化贝中油气集输工艺,贝中区块减少脱水站、污水站各1座。应用电加热集油后与掺水工艺相比减少掺水管道112km,减少集油阀组间8座。
Hulunbeier oilfield block decentralized, single-well low productivity, the ground system in accordance with the conventional process planning design million tons of capacity of ground construction investment reached 2.09 billion yuan. In order to reduce the investment in ground construction and improve the development benefit of oilfields, the scale-up and construction of Bell Oilfield in 2008 started to adopt the process of electric heating pipe + oil and gas gathering and transportation, simplifying the process of oil gathering in the ground and optimizing the oil and gas gathering and distribution process in Beizhong, Reduce dehydration stations, sewage stations each one. Application of electric heating after oil collection compared with the water-reducing process to reduce the water pipe 112km, to reduce the set of eight valve block.