河口村水库大坝为面板堆石坝,大坝建在深覆盖层上,大坝的主体———坝体的沉降变形是保证大坝坝体及混凝土面板安全的关键。文章介绍面板堆石坝坝体填筑质量控制管理。对坝体一期堆石体填筑过程严格管理,严把料源和工序控制,采用先进科技手段,保证了工程质量,加快施工进度,为后期混凝土面板施工赢得宝贵时间进行阐述。
The dam of Hekou Village is a concrete faced rockfill dam, and the dam is built on the deep overburden. The settlement and deformation of the dam, the main part of the dam, is the key to ensure the safety of the dam and the concrete face of the dam. The paper introduces the dam rockfill dam body filling quality control management. The first phase of rockfill dam body filling process of strict management, strict material source and process control, the use of advanced scientific and technological means to ensure the quality of the project to speed up the construction progress, for the latter part of the construction of concrete panels won valuable time elaborated.