津秦客运专线引入秦山地区的施工过渡方案,涉及运营部门较多,改建工程量大。在论述施工过渡方案的基本原则与思路的基础上,提出4个施工过渡方案,并从运营安全、施工作业干扰及难度、施工工期、市政配套工程、行包业务、旅客乘降条件和过渡工程总投资方面,进行方案技术经济比较并给出推荐方案。
The introduction of the Jinqin Passenger Dedicated Line into the Qinshan area construction transition program, involving more operating departments, reconstruction of large quantities. Based on the discussion of the basic principles and ideas of the construction transitional plan, four construction transitional plans are put forward. From the perspectives of operational safety, construction operation disturbance and difficulty, construction period, municipal supporting works, parcel service, passenger take-off and landing conditions and transitional engineering The total investment, the technical and economic programs to compare and give recommendations.