“八五”期间,上海梅山集团有限公司加强节能管理,依靠技术进步节约能源;吨铁综合能耗和吨铁可比能耗分别比“七五”期间下降37.9kg 标煤和29.56kg 标煤,节约标煤共31.9万 t,节省能源费1.276亿元,矿、铁、烧三项工序能耗全部达到国家一级水平。“八五”期间,梅山公司节能技改21项,完成投资556.3万元,节能效果大的重点项目有:烧结厂2台烧结机幕帘式点火器荣获国家经贸委、国家计委1994年节能科技成果奖、上海市1993年度优秀节能技改项目一等奖。他们采用热管技术,在烧结机机尾建成利用烟气余热的2~#余热锅炉也荣获上海市1994年优秀节能项目二等奖。动力厂6000kw 季节性发电机荣
During the “Eighth Five-Year Plan” period, Shanghai Meishan Group Co., Ltd. strengthened its energy conservation management and relied on technological progress to conserve energy; the comprehensive energy consumption per ton of iron and the comparable energy consumption per ton of iron decreased by 37.9 kg compared with the period of the “Seventh Five-Year Plan” and 29.56 respectively. Kg of coal, saving a total of 319,000 tons of standard coal, energy savings of 127.6 million yuan, mining, iron, and burn all three processes energy consumption reached the national level. During the “8th Five-Year Plan” period, 21 Meishan energy-saving technological transformation projects completed investment of 5.563 million yuan. Major projects with large energy-saving effect include: sintering plant 2 sets of sinter curtain igniters won the State Economic and Trade Commission and the State Planning Commission 1994 The annual energy conservation scientific and technological achievements award and the Shanghai Municipal Outstanding Energy-saving Technological Reform Project in 1993 were the first prize. They adopted heat pipe technology and built 2## waste heat boilers that use waste heat from the tail of the sinter machine. They also won the second prize of Shanghai Excellent Energy Conservation Project in 1994. Power Plant 6000kw Seasonal Generator Rong