各位领导、各位代表、同志们:我自2004年9月起担任威乳高速公路第二合同段项目经理,2005年任公司副总经理。2005年我的项目管理目标责任主要是完成施工产值9140万元,上交款1080万元(含青银二期前期投入250万元),职工工资及时发放和社保四项基金足额上缴,工程质量安全无事故,年度综合评比确保前三名。经过努力,全部完成各项责任指标,完成的施工产值和上交款是全公司最多的,而且在业主年终考核中还以总分第一名的优异成绩获得“威乳高速公路工程建设2005年度先进施工单位”奖牌。现将我的履职情况汇报如下,请审议。
Distinguished leaders, deputies, and comrades: I have been the project manager of the second contract section of Weimarao Expressway since September 2004 and the deputy general manager of the Company in 2005. In 2005, my goal of project management was mainly to complete the construction output value of 91.4 million yuan, pay 10.8 million yuan (including 2.5 million yuan of the previous period of Phase II of Green Bank), timely payout of staff salaries and full payment of four social security funds, No accident of quality and safety, the annual comprehensive assessment to ensure that the top three. After all efforts, all the responsibility indicators were fulfilled, the output value of the construction and the payment of the completed construction were the highest in the whole company, and the first place in the year-end assessment of the owner was also awarded “Excellent Breast Expressway Project Construction 2005 The annual advanced construction unit ”medal. Now I report the performance of their duties as follows, please consider.