为确保观音阁水库惟幕灌浆的质量,在施工中建立健全了全面质量管理体系,即由水库建设管理局、公司(承包商)、公司施工处三方联合管理,对施工中的质量实行三级管理制度,对关键工序实行签证单制度.防渗惟幕灌浆的质量评价则根据质量评定结果、压水试验的资料以及灌浆过程中单位注入量的递减规律分析来确定.从最后评价的结果看,灌浆质量是好的,均满足设计要求标准.
In order to ensure the quality of curtain grouting in Guanyinge Reservoir, a total quality management system has been established and perfected during construction. That is to say, the reservoir management bureau, the company (contractor) and the construction department of the company jointly manage the quality of the construction in three stages Management system, the key processes of the visa system. The quality evaluation of impermeable curtain curtain grouting is based on the quality assessment results, the information of the water pressure test and the decreasing law of the unit injection quantity during the grouting process. Judging from the results of the final evaluation, grouting quality is good, all meet the design requirements of the standard.