采用传统的单侧支模工艺施工,高基础底板高落差处砼的外观容易出现质量缺陷,甚至出现模板坍塌的现象。该文以X工程项目为例,设计高基础底板高落差处砼的施工方案。该工程的地下水位高,为确保结构自防水质量,必须一次性完成砼浇筑,导致单侧模板承受的侧压力大、支模条件差。通过分析影响X工程项目的基础底板高落差处砼外观质量因素的保障状况,提出改进侧向支撑固定方式、合理设置模板底部锚固点、编制砼专项施工方案等措施,使基础高落差处砼外观达到预期的质量目标。
With the traditional unilateral mold construction, the appearance of concrete with high base slab height is prone to quality defects and even the template collapses. Taking X project as an example, this paper designs the construction scheme of concrete with high base floor height difference. The groundwater level of the project is high. In order to ensure self-waterproofing quality of the structure, the concrete pouring must be completed once, resulting in large lateral pressure on the one-sided template and poor mold-supporting conditions. By analyzing the protection status of the concrete appearance quality factors affecting the height difference of the base slab of X project, some measures are proposed to improve the fixing method of lateral supports, reasonably set the anchorage points at the bottom of the formwork and compose the special construction scheme of concrete so that the concrete appearance Achieve the desired quality goals.