【摘 要】在高层建筑施之中,当扣件式钢管脚手架的搭设高度超过50m时,常采用分段悬挑或分段卸荷的措施进行搭设,并须进行专门设计。本文介绍分段卸荷装置的布置、设计计算要点及共应注意的一些问题,以供同行在作专门施工方案时参考。
【关键词】脚手架;卸荷;装置;设计;计算
Button up a type steel pipe scaffold cent segment the design calculation which unload a lotus to equip important point
Chen Guan-de
(Huazhou Construction engineering head office three company Huazhou Guangdong 525100)
【Abstract】In the key figures the building, be button up take of a type steel pipe scaffold to establish height over 50 m, often adoption cent segment hang to pick or cent the segment unload a lotus of the measure carry on taking to establish, and the beard carry on specialized design.This text introduction cent segment unload a lotus equip of decoration, design calculation important point and total should attention of some problem go together by provide at make specialized construction project reference.
【Key words】Scaffold;Unload a lotus;Equip;Design;Calculation
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)第5.3.7条规定:“单管立杆脚手架的搭设高度Hs 不家超过50m。”第5.3.8 条又规定:“高度超过50m的脚手架,可采用双管立杆、分段悬挑或分段卸荷等有交措施,必须量行专门设计。”分段卸荷措施,主要是分段卸荷装置的设计计算问题,笔者在此谈谈自己的一些体会。
1. 分段卸荷装置的布置
分段卸荷措施,是将脚手架全高分成几个高度段,然后用钢线绳将脚手架吊拉在主体建筑物上,将脚手架上的荷载卸荷给主体建筑物。
1.1 分段高度:沿脚手架全高进行分段,一般每段高度控制在12~18m。
1.2 水手吊点的间距:以3跨为宜(即3倍立杆纵距)。
1.3 斜拉钢绦绳:斜拉钢绦绳与脚手架的连结点必须设在脚手架的主节点外(即立杆纵向水平杆、横向水平杆交点处)并绕过节点处最下一根水平杆(纵向水平杆或横向水平杆)底部兜紧;斜拉钢绦绳与主体结构的连结点常设于框架柱、框架梁或其悬挑构件的封口梁上。需要注意的是,除了连结点设于框架柱外,在其他情况下,均应根据斜拉钢绦绳施加给主体结构的荷载,复核原设计的强度与变形是否满足设计要求。
1.4 预理吊环:斜拉钢绦绳是通过预埋吊环将所受的荷载传给主体结构的。因此,对预进埋在主体结构上的吊环,根据《混凝土结构设计规范》(GB50010-2002)有以下一些要求:吊环应采用HPB235级钢盘制作,严禁使用冷加工钢筋。吊环埋入混凝土的深度不应小于30d,并应焊接或绑扎在钢筋骨架上。
1.5 卡环:卡环(卸甲、卸扣)是用来连斜拉钢绦绝和预理吊环的构件。可根据斜拉钢绦绳的直径及其所受的拉力,按《建筑施工安全技术手册》附表3-12-7选用。
1.6 钢绦绳夹:钢绦绳夹是用来绳端固定或连接用。其所需数量使用间距,可按《建筑施工手册》第四版表14-10选用。
2. 设计计算要点
2.1 拟定脚手架的搭设方案
2.1.1 拟定脚手架的搭设尺寸:立杆纵距la、立杆横距lb、纵向水平杆步距h 及连墙件设置。
2.1.2 拟定作业层层数n1和铺板层层数n2(规范规定:自顶层作业层的脚手板往下计,宜每隔12m 满铺一层脚手板)。
2.1.3 确定脚手板和档脚板所用的材料,挥规范分别查出其自重标准值δK1、δK2。
2.1.4 栏杆设置:脚手架外立面因要设置栏杆和固定安全网每部需要增加的栏杆数n3(一般取n3=2)。每米栏杆及其连接扣件的自重标准值δk3=0.0384+0.0132la(式中0.0384为每米钢管自重, 0.0132为每个直角扣件自重)。
2.1.5 安全网:脚手架的外立面需挂2000目/100cm2 以上的密目安全网,其自重标准值可近似取δk4=0.005KN/m2。
2.1.6 钢管理规格:一般取用48×3.5钢管,其自重标准值为0.0384KN/m。
2.1.7 确定脚手架的搭设高度H及分段高度H1、水平吊点的间距б。
2.2 计算脚手架全高一个跨距内总的荷载标准值。
2.2.1 结构自重标准值NG1K(可查《规范》附表A表A-1)。
2.2.1 构配件自重标准值NG2K。
包括脚手板自重、附加的纵向水平杆或横向水平杆及其扣件自重、档脚板自重以及全填闭安全网及栏杆的自重标准值。
2.2.2 施工荷载标准值Nak。
计算时施工均布活荷载,装修用脚手架δK=2KN/m2,结构用脚手架δK=3KN/m2。
2.3 计算脚手架全高一个跨距内总的荷载设计值N。
N=1.2(NG1K+NG2K)+1.4NQK
2.4 分段卸荷装置的计算。
脚手架的卸荷装置如图1所示。
设沿全高将脚手架分为几个卸荷段,则在竖直方向上主体结构公有(n-1)个吊点,每个吊点有两根钢绦绳,因些,在一个计算单元内(3个立杆纵距)共需钢绦绳2(n-1)根,其所受的荷载设计值合计为3N。
图1 脚手架卸荷示意图
2.4.1 每一吊点处钢绦绳录受的荷载设计值P:
P=3N2(n-1)•Kχ (1)
式中Kχ——考虑两根钢绦绳拉紧程度不一致造成受力不均而采用的“不均匀系数”,取Kχ=1.5。
2.4.2 钢绦绳的拉力计算。
2.4.2.1 外排吊点处钢绦绳的拉力TA:
TA=Psinα(2)
2.4.2.2 内排吊点处钢绦绳的拉力TB:
TB=Psinβ(3)
从公式(2)、(3)可知α和β角越大,TB和TB越小,故宜取 tgα≥5。
2.4.2.3 吊点处横向水平杆水平分为TAB:
TAB=Pctgα+Pctgβ=P(ctgα+ctgβ) (4)
2.4.3 钢绦绳及卡环的选择。
据(2)、(3)式的计算结果,按下式选择钢绦绳:
〔Fg〕=2FgK>TA(或TB) (5)
式中〔Fg〕—钢绦绳容许拉力(KN);
Fg—钢绦绳的钢绦破断拉力总和(KN),可从《建筑施工工程师手册》表11-4查得;
α—考虑钢绦绳之间荷载不均匀系数,对6×19、6×37、6×61鋼绦绳,α分别取0.85,0.82,0.80;
K——安全系数,取K=8。
卡环按上文提到的方法选择。
2.4.4 预埋吊环选择计算。
据《混凝土结构设计规范》(GB50010-2002),每个吊环可按两个截面计算,吊环的应力不应大于50N/mm2,故吊环的截面积(mm2)按下式计算:
A=TA(或TB)2×50(6)式中TA、TB——钢绦绳的拉力(N)。
需要注意的是,公式(6)是两根钢绦绳分别设置一个吊环的计算公式;若两根钢绦绳只设置一个吊环,则应按下面方法计算出两根钢绦绳的拉力TA和TB的合力T,然后再按公式(6)选择吊环:
如图2所示,设两根钢绦绳的拉力分别为TA和TB,则共合力T为:T=TA2+TB2-2TA•TB•cos4(7)
式中:4=180+α-β。α,β见图1。
2.4.5 抗滑验算。
图2 合力T求解示意图
图3 垂直抗滑示意图
2.4.5.1 水平抗滑验算公式为
TAB <2×8=16KN (8)
式中2×8是每根横向水平杆按2个扣件计算,每个直角扣件的抗滑承载力设计值为8KN。
若不满足公式(17)的要求,可另增加横向水平杆顶住主体建筑物。
2.4.5.2 垂直抗滑验算。
按下式计算吊点处所需的抗滑扣件数n: n=P8(9)
式中P-吊点处的垂直力(KN);
8——一个直角扣件的抗滑承载力(KN)。
一个步距内立杆已有2个扣件,所以吊点处每根立杆需要增加的扣件数为(n-2)个。
抗滑措施可在吊点步距内增设短立杆,上下与纵向水平杆顶紧,并用增加的扣件与原立杆扣紧(如图3所示)。
最后需要指出的是,为使斜拉钢绦绳各吊点之间同步受力,施工时用手动葫芦拉紧,以避免脚手架在受力后产生变形不一的现象。
[文章编号]1619-2737(2011)02-14-16
[作者简介] 陈观德,男,籍贯:广东省化州市,单位:广东省化州市建筑工程总公司第三公司,职称:工程师。
【关键词】脚手架;卸荷;装置;设计;计算
Button up a type steel pipe scaffold cent segment the design calculation which unload a lotus to equip important point
Chen Guan-de
(Huazhou Construction engineering head office three company Huazhou Guangdong 525100)
【Abstract】In the key figures the building, be button up take of a type steel pipe scaffold to establish height over 50 m, often adoption cent segment hang to pick or cent the segment unload a lotus of the measure carry on taking to establish, and the beard carry on specialized design.This text introduction cent segment unload a lotus equip of decoration, design calculation important point and total should attention of some problem go together by provide at make specialized construction project reference.
【Key words】Scaffold;Unload a lotus;Equip;Design;Calculation
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)第5.3.7条规定:“单管立杆脚手架的搭设高度Hs 不家超过50m。”第5.3.8 条又规定:“高度超过50m的脚手架,可采用双管立杆、分段悬挑或分段卸荷等有交措施,必须量行专门设计。”分段卸荷措施,主要是分段卸荷装置的设计计算问题,笔者在此谈谈自己的一些体会。
1. 分段卸荷装置的布置
分段卸荷措施,是将脚手架全高分成几个高度段,然后用钢线绳将脚手架吊拉在主体建筑物上,将脚手架上的荷载卸荷给主体建筑物。
1.1 分段高度:沿脚手架全高进行分段,一般每段高度控制在12~18m。
1.2 水手吊点的间距:以3跨为宜(即3倍立杆纵距)。
1.3 斜拉钢绦绳:斜拉钢绦绳与脚手架的连结点必须设在脚手架的主节点外(即立杆纵向水平杆、横向水平杆交点处)并绕过节点处最下一根水平杆(纵向水平杆或横向水平杆)底部兜紧;斜拉钢绦绳与主体结构的连结点常设于框架柱、框架梁或其悬挑构件的封口梁上。需要注意的是,除了连结点设于框架柱外,在其他情况下,均应根据斜拉钢绦绳施加给主体结构的荷载,复核原设计的强度与变形是否满足设计要求。
1.4 预理吊环:斜拉钢绦绳是通过预埋吊环将所受的荷载传给主体结构的。因此,对预进埋在主体结构上的吊环,根据《混凝土结构设计规范》(GB50010-2002)有以下一些要求:吊环应采用HPB235级钢盘制作,严禁使用冷加工钢筋。吊环埋入混凝土的深度不应小于30d,并应焊接或绑扎在钢筋骨架上。
1.5 卡环:卡环(卸甲、卸扣)是用来连斜拉钢绦绝和预理吊环的构件。可根据斜拉钢绦绳的直径及其所受的拉力,按《建筑施工安全技术手册》附表3-12-7选用。
1.6 钢绦绳夹:钢绦绳夹是用来绳端固定或连接用。其所需数量使用间距,可按《建筑施工手册》第四版表14-10选用。
2. 设计计算要点
2.1 拟定脚手架的搭设方案
2.1.1 拟定脚手架的搭设尺寸:立杆纵距la、立杆横距lb、纵向水平杆步距h 及连墙件设置。
2.1.2 拟定作业层层数n1和铺板层层数n2(规范规定:自顶层作业层的脚手板往下计,宜每隔12m 满铺一层脚手板)。
2.1.3 确定脚手板和档脚板所用的材料,挥规范分别查出其自重标准值δK1、δK2。
2.1.4 栏杆设置:脚手架外立面因要设置栏杆和固定安全网每部需要增加的栏杆数n3(一般取n3=2)。每米栏杆及其连接扣件的自重标准值δk3=0.0384+0.0132la(式中0.0384为每米钢管自重, 0.0132为每个直角扣件自重)。
2.1.5 安全网:脚手架的外立面需挂2000目/100cm2 以上的密目安全网,其自重标准值可近似取δk4=0.005KN/m2。
2.1.6 钢管理规格:一般取用48×3.5钢管,其自重标准值为0.0384KN/m。
2.1.7 确定脚手架的搭设高度H及分段高度H1、水平吊点的间距б。
2.2 计算脚手架全高一个跨距内总的荷载标准值。
2.2.1 结构自重标准值NG1K(可查《规范》附表A表A-1)。
2.2.1 构配件自重标准值NG2K。
包括脚手板自重、附加的纵向水平杆或横向水平杆及其扣件自重、档脚板自重以及全填闭安全网及栏杆的自重标准值。
2.2.2 施工荷载标准值Nak。
计算时施工均布活荷载,装修用脚手架δK=2KN/m2,结构用脚手架δK=3KN/m2。
2.3 计算脚手架全高一个跨距内总的荷载设计值N。
N=1.2(NG1K+NG2K)+1.4NQK
2.4 分段卸荷装置的计算。
脚手架的卸荷装置如图1所示。
设沿全高将脚手架分为几个卸荷段,则在竖直方向上主体结构公有(n-1)个吊点,每个吊点有两根钢绦绳,因些,在一个计算单元内(3个立杆纵距)共需钢绦绳2(n-1)根,其所受的荷载设计值合计为3N。
图1 脚手架卸荷示意图
2.4.1 每一吊点处钢绦绳录受的荷载设计值P:
P=3N2(n-1)•Kχ (1)
式中Kχ——考虑两根钢绦绳拉紧程度不一致造成受力不均而采用的“不均匀系数”,取Kχ=1.5。
2.4.2 钢绦绳的拉力计算。
2.4.2.1 外排吊点处钢绦绳的拉力TA:
TA=Psinα(2)
2.4.2.2 内排吊点处钢绦绳的拉力TB:
TB=Psinβ(3)
从公式(2)、(3)可知α和β角越大,TB和TB越小,故宜取 tgα≥5。
2.4.2.3 吊点处横向水平杆水平分为TAB:
TAB=Pctgα+Pctgβ=P(ctgα+ctgβ) (4)
2.4.3 钢绦绳及卡环的选择。
据(2)、(3)式的计算结果,按下式选择钢绦绳:
〔Fg〕=2FgK>TA(或TB) (5)
式中〔Fg〕—钢绦绳容许拉力(KN);
Fg—钢绦绳的钢绦破断拉力总和(KN),可从《建筑施工工程师手册》表11-4查得;
α—考虑钢绦绳之间荷载不均匀系数,对6×19、6×37、6×61鋼绦绳,α分别取0.85,0.82,0.80;
K——安全系数,取K=8。
卡环按上文提到的方法选择。
2.4.4 预埋吊环选择计算。
据《混凝土结构设计规范》(GB50010-2002),每个吊环可按两个截面计算,吊环的应力不应大于50N/mm2,故吊环的截面积(mm2)按下式计算:
A=TA(或TB)2×50(6)式中TA、TB——钢绦绳的拉力(N)。
需要注意的是,公式(6)是两根钢绦绳分别设置一个吊环的计算公式;若两根钢绦绳只设置一个吊环,则应按下面方法计算出两根钢绦绳的拉力TA和TB的合力T,然后再按公式(6)选择吊环:
如图2所示,设两根钢绦绳的拉力分别为TA和TB,则共合力T为:T=TA2+TB2-2TA•TB•cos4(7)
式中:4=180+α-β。α,β见图1。
2.4.5 抗滑验算。
图2 合力T求解示意图
图3 垂直抗滑示意图
2.4.5.1 水平抗滑验算公式为
TAB <2×8=16KN (8)
式中2×8是每根横向水平杆按2个扣件计算,每个直角扣件的抗滑承载力设计值为8KN。
若不满足公式(17)的要求,可另增加横向水平杆顶住主体建筑物。
2.4.5.2 垂直抗滑验算。
按下式计算吊点处所需的抗滑扣件数n: n=P8(9)
式中P-吊点处的垂直力(KN);
8——一个直角扣件的抗滑承载力(KN)。
一个步距内立杆已有2个扣件,所以吊点处每根立杆需要增加的扣件数为(n-2)个。
抗滑措施可在吊点步距内增设短立杆,上下与纵向水平杆顶紧,并用增加的扣件与原立杆扣紧(如图3所示)。
最后需要指出的是,为使斜拉钢绦绳各吊点之间同步受力,施工时用手动葫芦拉紧,以避免脚手架在受力后产生变形不一的现象。
[文章编号]1619-2737(2011)02-14-16
[作者简介] 陈观德,男,籍贯:广东省化州市,单位:广东省化州市建筑工程总公司第三公司,职称:工程师。