章邱修防段今年增加的抽槽换土堤基加固工程,在时间短任务繁重的情况下,汛前完成了任务,成绩还是很大的。但由于对堤防加固工程的意义认识不足,存在着任务观点,和官僚主义,致使施工中造成不少的损失。特分别介绍于后作为今后堤防加固工程的教训。①须动员的一千多民工未列入包工包做发动计划。原有包工基础的民工因支持外县,留县的包工
Chapter Qiu Xiu anti-segment This year to increase the pumping tank earthwork for embankment reinforcement project, in the case of heavy workload, the completion of the task before the flood, the result is still great. However, due to lack of understanding of the significance of the embankment reinforcement project, there is a task point of view and bureaucracy, resulting in a lot of construction losses. Special introduced later as the levee reinforcement project in the future lessons. ① More than a thousand migrant workers to be mobilized have not been included in the construction package plan. The original contract-based migrant workers because of the support of counties, leaving the county contractor