论文部分内容阅读
从1955年5月西德结束被占领状态,获准和平利用核能算起,西德核技术的发展已经历了30年,至目前已有20座核电站供应电力,总功率达16.5 GW。在核燃料循环领域内,1985年是西德有转折性突破的一年,其重要事件有:西德政府在一月份对两种辐照核燃料处理方案进行了抉择;西德核燃料后处理公司(DWK)决定了后处理厂址;Gronau浓缩铀工厂按期投产;玻璃固化装置PAMELA于八月份投入热运行。
From May 1955, when West Germany ended its occupation and was allowed to make peaceful use of nuclear energy, West Germany’s nuclear technology has been developing for 30 years. To date, 20 nuclear power stations have supplied electricity with a total power of 16.5 GW. In the area of nuclear fuel cycle, there was a turning point in West Germany in 1985 with important events such as the West German government making a decision on two options for handling irradiated nuclear fuel in January; the West German nuclear fuel reprocessing company (DWK ) Determined the reprocessing site; the Gronau uranium plant went on schedule and the glass curing unit PAMELA was put into thermal operation in August.