通过对密排管座集箱的地面组对工艺进行优化,分析了工艺中的关键点,得出最佳的施工方案,即按管座处于水平位摆放集箱、自上而下、按行进行组对、将射线探伤安排在夜间进行、安排能胜任全位置焊接的优秀焊工施焊。该工艺具有以下特点:①提高施工安全系数、方便钳工组对;②消除焊接困难位置,降低焊接难度,提高焊缝质量;③方便焊接检验,减少了工序之间的时间冲突,缩短施工工期。
By optimizing the process of the ground group of the header of the close-packed tube header, the key points in the process are analyzed and the best construction scheme is obtained, that is, the header is placed horizontally in the tube base, and from top to bottom, Conduct a group of pairs of radiological testing scheduled for the night to arrange for full-position welding qualified welder welding. The process has the following characteristics: ① improve the construction safety factor to facilitate fitter group pairs; ② eliminate the welding difficult position, reduce the welding difficulty and improve the quality of the weld; ③ facilitate welding inspection, reduce the time conflict between processes and shorten the construction period.