某工程高大钢管混凝土柱因施工不当,柱顶出现较大偏位需纠偏修复。根据其结构特点,搭设托梁反顶修复平台并安装顶升设备,依据计算所得反顶预应力,对钢管混凝土柱进行托梁顶升卸载,再将其偏位段拆除并安装新钢管,采用高性能自密实注浆料灌注修复,待注浆料强度满足要求后,移除顶升设备及修复平台。托梁反顶修复过程中进行了结构变形的全过程监测,以保证施工质量及安全。因各方面准备充分且实施顺利,托梁纠偏取得了良好效果。
Due to improper construction of a large high-rise concrete-filled steel tubular column, a large deviation at the top of the column requires corrective repair. According to its structural features, erecting joist anti-top repair platform and installation of lifting equipment, according to the calculated top anti-top prestressed concrete column to carry out joist lifting, and then remove the deviation of the section and install new steel pipe, high performance Self-compact grouting material filling repair, to be grouting material strength to meet the requirements, remove the lifting equipment and repair platform. Joist anti-top repair process carried out the whole process of structural deformation monitoring in order to ensure the construction quality and safety. Due to the preparation of all aspects and the successful implementation of joist correction has achieved good results.