郑州至开封110千伏高压输变电工程,线路全长94.8公里,杆塔共422基(其中铁塔5基,高达41米),变电站容量为2万千伏安。整个线路80%以上经过流沙地带,运输、施工都比较困难,在开工前,材料、设备、铁塔和金具构件加工大部无着落,根据开封化肥厂生产需要,省委指示要在11月20日完工送电,时间紧迫,任务繁重。我们在省委、省人委、市委、省电力工业局正确领导下,在总路线光辉照耀下,在各兄弟单位大力支援下,紧
From Zhengzhou to Kaifeng, the 110 kV high-voltage power transmission project has a total length of 94.8 kilometers, a total of 422 bases (of which the iron tower is 5 bases, up to 41 meters), and the substation capacity is 20 thousand kVA. More than 80% of the entire line passes through the quicksand zone. Transportation and construction are difficult. Before the start of construction, most of the processing of materials, equipment, towers, and hardware components was not done. According to the production needs of the Kaifeng Chemical Fertilizer Plant, the provincial Party committee instructed it to be on November 20. Completion of power transmission, time is pressing, heavy tasks. We are under the correct leadership of the Provincial Party Committee, the Provincial People’s Committee, the Municipal Party Committee, and the Provincial Electric Power Industry Bureau. Under the brilliance of the general line, with the strong support of all brothers and