【摘 要】 现代的建筑工程既要保证工程的质量又要追求的进度,但裂缝的产生使工程的质量和进度相互统一中又产生矛盾。但是,通过后浇带的技术控制可以有效缓解混凝土结构出现的施工裂缝。本文将从后浇带的定义、特征和主要功能进行分析,并在此基础上体现后浇带在混凝土施工中的重要作用。本文第三部分将对后浇带的施工技术和在施工中出现的各种问题进行分析,并提出解决方案。
【关键词】 建筑施工;后浇带;功能作用;施工技术
【Abstract】 Modern construction is necessary to ensure the quality of the project but also the pursuit of progress, but the quality and progress of cracks in unity with each other so that the project has produced contradictory. However, the technical control after pouring through the construction zone can effectively alleviate the cracks of concrete structures arise. This article from the band after pouring definition, characteristics and key functions to analyze and reflect on the important role of the poured concrete construction with on this basis. After the third part of this article will be poured with construction technology and the emergence of various problems in the construction of the analysis, and propose solutions
【Key Words】 Construction; After pouring belt; construction technology; functional role
引言:
后澆带是一种防裂缝措施。由于钢筋混凝土在不同的温度下收缩和膨胀的程度不同,产生有害的裂缝是不可避免的。因此需要在结构设计和施工规范的约束下对基础、墙、梁、板等构件留设施工缝,将结构暂时划分为多个部分,通过构件的自然物理收缩或膨胀的原理,在一定的时间之后再进行混凝土的填充,将多个结构连成一个统一的整体。
一、施工后浇带的功能
后浇带,也称施工后浇带。按作用分可分为三种:用于解决高层主体与低层裙房的差异沉降者,称为后浇沉降带;用于解决钢筋混凝土收缩变形者,称为后浇收缩带;用于解决混凝土温度应力者,称为后浇温度带。
这种后浇带一般具有多种变形缝的功能,设计时应考虑以一种功能为主,其他功能为辅。施工后浇带是整个建筑物,包括基础及上部结构施工中的预留缝(“缝”很宽,故称为“带”),待主体结构完成,将后浇带混凝土补齐后,这种“缝”即不存在,既在整个结构施工中解决了高层主楼与低居裙房的差异沉降,又达到了不设永久变形缝的目的。
二、施工后浇带的做法
一般高层主楼与低层裙房的基础同时施工,这样回填土后场地平整,便于上部结构施工。对于上部结构,无论是高层主楼与低层裙房同时施工,还是先施工高层,后施工低层,同样要按施工图预留施工后浇带。
对高层主楼与低层裙房连接的基础梁、上部结构的梁和板,要预留出施工后浇带,待主楼与裙房主体完工后(有条件时再推迟一些时间),再用微膨胀混凝土将它浇筑起来,使两侧地梁、上部梁和板连接成一个整体。这样做的目的是为了把高层与低层的沉降差异减小一些,因为高层主楼完成之后,一般情况下,其沉降量已完成最终沉降量的60%-80%,剩下的沉降量就小多了,这时再补齐施工后浇带混凝土,二者差异沉降量就较小-些,这部分差异沉降引起的结构内力,可由不设永久变形缝的结构承担。对于施工后浇收缩带,宜在主体结构完工两个月后浇筑混凝土,这时估计混凝土收缩量已完成60%以上。
施工后浇带的位置宜选在结构受力较小的部位,一般在梁、板的弯矩反弯点附近,此位置弯矩较小,剪力也不大;也可选在梁、板的中部,弯矩虽大,但剪力很小。在施工后浇带处,混凝土虽为后浇,但钢筋不能断。如果梁、板跨度不大,可一次配足钢筋;如果跨度较大,可按规定断开,在补齐混凝土前焊接好。后浇带的配筋,应能承担由浇筑混凝土成为-整体后的差异沉降而产生的内力,一般可按差异沉降变形反算为内力,而在配筋上予以加强。后浇带的宽度应考虑便于施工操作,并按结构构造要求而定,一般宽度以700-1000mm为宜。
施工后浇带的断面形式应考虑浇筑混凝土后连接牢固,一般宜避免留直缝。对于板,可留斜缝;对于梁及基础,可留企口缝,而企口缝又有多种形式,可根据结构断面情况确定。
三、后浇带施工技术分析
(一)时间选择
通常情况下混凝土构件的收缩在两个月之内会完毕。而对于高层建筑和裙楼的结构和基础而言,则要等沉降完成之后开始浇筑后浇带。裙楼和高层建筑的主体部分一般是同时施工的,但是裙楼的施工量小而主楼的施工量大,在裙楼完成后,主楼的施工尚未完成,实际上裙楼的荷载产生的沉降在前,主楼的沉降在后,且主楼荷载造成的沉降多于裙楼的荷载,因此必须等主楼完全沉降完方可进行后浇带砼的施工。由于不同的施工季节、施工材料,一些需要延后浇筑时间的工程则要在设计图纸上体现出来。 (二)材料选择
后浇带浇筑前要将裂缝全面清除浮渣,排除积水,保持后浇带两边的构件表面湿润24小时以上。选择的混凝土是无收缩混凝土——膨胀水泥或添加膨胀外加剂的普通水泥配置的混凝土。为了使后浇带的强度高于所连接的构件,施工前必须加入早强减水剂,对混凝土进行认真的配比和振捣。
(三)后浇带前期准备
在前期的准备工作中,主要是对模板的预设。当裙楼连接主楼的跨度过大时,支撑它们的地下室大梁就会出现荷载过大,严重的还会超出钢支撑扣件所能承受的压力,造成螺栓的破坏。为了避免这种情况的发生,在混凝土的浇筑之前,必须预设钢丝网模板。对于这种钢丝网板的要求也相对较严格,除了钢丝网格均匀统一和钢丝粗细统一以外,模板的强度、刚度和稳定性也必须有质量的保证。总之,模板的预设必须严格按照施工图纸进行,不得有半点纰漏。如果需要进行新老界面的粘结工程,新旧混凝土的结合面是一个薄弱环节,其界面粘结强度一般都低于整浇混凝土的强度,极大地影响了结构的可靠性。影响新老混凝土结合面粘接性能的因素较多,但处理新老混凝土结合面方法需掌握以下几个原则:合理有效的表面处理;根据实际情况针对性地选择粘结剂;严格控制新混凝土浇筑时间;及时的养护措施。
(四)浇筑混凝土
首先必须按照施工方案严格进行施工。第二、水平后浇带的浇筑要将钢丝网模板的侧压力控制在正常范围之内;垂直后浇带的浇筑则要将混凝土充分振搗,振捣的时候要避免振捣器的振捣动作将钢丝网破坏。第三、注意振捣器与模板的距离以防止混凝土水泥浆流失。
(五)处理垂直施工缝
垂直施工缝的混凝土浇筑后达到初凝时就要用压力水冲洗直至出现骨料,并将钢丝网冲洗干净。为了避免错过冲洗时间,施工图纸要对时间进行预设,必要时要有专人负责检查。
(六)后浇带施工温度选择
后浇带砼要选择适合的浇筑温度,以保证新老砼结合良好。最好的温度是10摄氏度,这符合热力学的收缩和膨胀的最佳结合点。后浇带砼在浇筑完毕后要在两天之后选择适当的时间收关,防止砼出现干裂,最佳的时间是早上或傍晚。
(七)后浇带的保护
后浇带的施工缝必须避免杂质和水长时间滞留。通常在后浇带缝的两端或两侧采用设置挡水砖或在后浇带内壁上涂抹防水砂浆的措施来完成保护;“后浇带的施工缝处理完毕并清理干净后,在顶部用木模板或铁皮封盖,并用砂浆做出挡水带,四周设临时栏杆围护,以免施工过程中污染钢筋,堆积垃圾。”
四、施工中存在的问题以及解决方法
(一)材料质量上的问题
混凝土的质量直接关系到整栋大楼的质量问题,因此必须保证混凝土浇筑的严格性。混凝土的质量主要体现在两个方面,一个是不跑浆,一个是不会留直槎。跑浆会破坏建筑,而留直槎会导致后浇带出的木模出现过大的缝隙,混凝土因此漏料,以至于砼的密度不达标。所以,要保证混凝土的质量,必须留成斜坡槎。
(二)各种客观因素的影响
这些因素的存在,往往会导致施工不能够按照正常的进度完成,而且有的时候还会出现上半部分完成、下半部分停工的现象。这时候出现的后浇筑浇筑混凝土的情况,会造成更加严重的裂缝,因为它所引起的沉降破换了结构。那么,针对这种情况,要用高强度混凝土和内置高强度钢筋的方法来减缓上半部分工程施工时所形成的结构内应力。
五、结束语
鉴于后浇带的范围日益广泛,不仅用于高层主楼与低层裙房连接处,对于超长的多层或高层框架结构,虽不存在差异沉降问题,但为解决钢筋混凝土的收缩变形或混凝土的收缩应力,也采用后浇收缩带或后浇温度带,因此,后浇带的施工问题应引起高度重视,后浇带应按设计要求预留,一定要留企口缝,并按规定时间灌注混凝土,灌注前应将表面清理干净,将钢筋加以整理或施焊,然后浇注早强、无收缩水泥配制的混凝土或膨胀混凝土,浇注后加强养护。施工中要采取有力措施,加强监督与检查,以确保后浇带的施工质量。
参考文献:
[1]刘木华.试论建筑施工中后浇带的功能作用与施工技术分析.科技创新与应用[J]. 2013,[3].
[2]杨贻彬.后浇带施工的重要作用和技术手段浅析[J].科技资讯,2009(14).
[3]秦桂娟等. [M].中国建筑工业出版社,2010(11).
【关键词】 建筑施工;后浇带;功能作用;施工技术
【Abstract】 Modern construction is necessary to ensure the quality of the project but also the pursuit of progress, but the quality and progress of cracks in unity with each other so that the project has produced contradictory. However, the technical control after pouring through the construction zone can effectively alleviate the cracks of concrete structures arise. This article from the band after pouring definition, characteristics and key functions to analyze and reflect on the important role of the poured concrete construction with on this basis. After the third part of this article will be poured with construction technology and the emergence of various problems in the construction of the analysis, and propose solutions
【Key Words】 Construction; After pouring belt; construction technology; functional role
引言:
后澆带是一种防裂缝措施。由于钢筋混凝土在不同的温度下收缩和膨胀的程度不同,产生有害的裂缝是不可避免的。因此需要在结构设计和施工规范的约束下对基础、墙、梁、板等构件留设施工缝,将结构暂时划分为多个部分,通过构件的自然物理收缩或膨胀的原理,在一定的时间之后再进行混凝土的填充,将多个结构连成一个统一的整体。
一、施工后浇带的功能
后浇带,也称施工后浇带。按作用分可分为三种:用于解决高层主体与低层裙房的差异沉降者,称为后浇沉降带;用于解决钢筋混凝土收缩变形者,称为后浇收缩带;用于解决混凝土温度应力者,称为后浇温度带。
这种后浇带一般具有多种变形缝的功能,设计时应考虑以一种功能为主,其他功能为辅。施工后浇带是整个建筑物,包括基础及上部结构施工中的预留缝(“缝”很宽,故称为“带”),待主体结构完成,将后浇带混凝土补齐后,这种“缝”即不存在,既在整个结构施工中解决了高层主楼与低居裙房的差异沉降,又达到了不设永久变形缝的目的。
二、施工后浇带的做法
一般高层主楼与低层裙房的基础同时施工,这样回填土后场地平整,便于上部结构施工。对于上部结构,无论是高层主楼与低层裙房同时施工,还是先施工高层,后施工低层,同样要按施工图预留施工后浇带。
对高层主楼与低层裙房连接的基础梁、上部结构的梁和板,要预留出施工后浇带,待主楼与裙房主体完工后(有条件时再推迟一些时间),再用微膨胀混凝土将它浇筑起来,使两侧地梁、上部梁和板连接成一个整体。这样做的目的是为了把高层与低层的沉降差异减小一些,因为高层主楼完成之后,一般情况下,其沉降量已完成最终沉降量的60%-80%,剩下的沉降量就小多了,这时再补齐施工后浇带混凝土,二者差异沉降量就较小-些,这部分差异沉降引起的结构内力,可由不设永久变形缝的结构承担。对于施工后浇收缩带,宜在主体结构完工两个月后浇筑混凝土,这时估计混凝土收缩量已完成60%以上。
施工后浇带的位置宜选在结构受力较小的部位,一般在梁、板的弯矩反弯点附近,此位置弯矩较小,剪力也不大;也可选在梁、板的中部,弯矩虽大,但剪力很小。在施工后浇带处,混凝土虽为后浇,但钢筋不能断。如果梁、板跨度不大,可一次配足钢筋;如果跨度较大,可按规定断开,在补齐混凝土前焊接好。后浇带的配筋,应能承担由浇筑混凝土成为-整体后的差异沉降而产生的内力,一般可按差异沉降变形反算为内力,而在配筋上予以加强。后浇带的宽度应考虑便于施工操作,并按结构构造要求而定,一般宽度以700-1000mm为宜。
施工后浇带的断面形式应考虑浇筑混凝土后连接牢固,一般宜避免留直缝。对于板,可留斜缝;对于梁及基础,可留企口缝,而企口缝又有多种形式,可根据结构断面情况确定。
三、后浇带施工技术分析
(一)时间选择
通常情况下混凝土构件的收缩在两个月之内会完毕。而对于高层建筑和裙楼的结构和基础而言,则要等沉降完成之后开始浇筑后浇带。裙楼和高层建筑的主体部分一般是同时施工的,但是裙楼的施工量小而主楼的施工量大,在裙楼完成后,主楼的施工尚未完成,实际上裙楼的荷载产生的沉降在前,主楼的沉降在后,且主楼荷载造成的沉降多于裙楼的荷载,因此必须等主楼完全沉降完方可进行后浇带砼的施工。由于不同的施工季节、施工材料,一些需要延后浇筑时间的工程则要在设计图纸上体现出来。 (二)材料选择
后浇带浇筑前要将裂缝全面清除浮渣,排除积水,保持后浇带两边的构件表面湿润24小时以上。选择的混凝土是无收缩混凝土——膨胀水泥或添加膨胀外加剂的普通水泥配置的混凝土。为了使后浇带的强度高于所连接的构件,施工前必须加入早强减水剂,对混凝土进行认真的配比和振捣。
(三)后浇带前期准备
在前期的准备工作中,主要是对模板的预设。当裙楼连接主楼的跨度过大时,支撑它们的地下室大梁就会出现荷载过大,严重的还会超出钢支撑扣件所能承受的压力,造成螺栓的破坏。为了避免这种情况的发生,在混凝土的浇筑之前,必须预设钢丝网模板。对于这种钢丝网板的要求也相对较严格,除了钢丝网格均匀统一和钢丝粗细统一以外,模板的强度、刚度和稳定性也必须有质量的保证。总之,模板的预设必须严格按照施工图纸进行,不得有半点纰漏。如果需要进行新老界面的粘结工程,新旧混凝土的结合面是一个薄弱环节,其界面粘结强度一般都低于整浇混凝土的强度,极大地影响了结构的可靠性。影响新老混凝土结合面粘接性能的因素较多,但处理新老混凝土结合面方法需掌握以下几个原则:合理有效的表面处理;根据实际情况针对性地选择粘结剂;严格控制新混凝土浇筑时间;及时的养护措施。
(四)浇筑混凝土
首先必须按照施工方案严格进行施工。第二、水平后浇带的浇筑要将钢丝网模板的侧压力控制在正常范围之内;垂直后浇带的浇筑则要将混凝土充分振搗,振捣的时候要避免振捣器的振捣动作将钢丝网破坏。第三、注意振捣器与模板的距离以防止混凝土水泥浆流失。
(五)处理垂直施工缝
垂直施工缝的混凝土浇筑后达到初凝时就要用压力水冲洗直至出现骨料,并将钢丝网冲洗干净。为了避免错过冲洗时间,施工图纸要对时间进行预设,必要时要有专人负责检查。
(六)后浇带施工温度选择
后浇带砼要选择适合的浇筑温度,以保证新老砼结合良好。最好的温度是10摄氏度,这符合热力学的收缩和膨胀的最佳结合点。后浇带砼在浇筑完毕后要在两天之后选择适当的时间收关,防止砼出现干裂,最佳的时间是早上或傍晚。
(七)后浇带的保护
后浇带的施工缝必须避免杂质和水长时间滞留。通常在后浇带缝的两端或两侧采用设置挡水砖或在后浇带内壁上涂抹防水砂浆的措施来完成保护;“后浇带的施工缝处理完毕并清理干净后,在顶部用木模板或铁皮封盖,并用砂浆做出挡水带,四周设临时栏杆围护,以免施工过程中污染钢筋,堆积垃圾。”
四、施工中存在的问题以及解决方法
(一)材料质量上的问题
混凝土的质量直接关系到整栋大楼的质量问题,因此必须保证混凝土浇筑的严格性。混凝土的质量主要体现在两个方面,一个是不跑浆,一个是不会留直槎。跑浆会破坏建筑,而留直槎会导致后浇带出的木模出现过大的缝隙,混凝土因此漏料,以至于砼的密度不达标。所以,要保证混凝土的质量,必须留成斜坡槎。
(二)各种客观因素的影响
这些因素的存在,往往会导致施工不能够按照正常的进度完成,而且有的时候还会出现上半部分完成、下半部分停工的现象。这时候出现的后浇筑浇筑混凝土的情况,会造成更加严重的裂缝,因为它所引起的沉降破换了结构。那么,针对这种情况,要用高强度混凝土和内置高强度钢筋的方法来减缓上半部分工程施工时所形成的结构内应力。
五、结束语
鉴于后浇带的范围日益广泛,不仅用于高层主楼与低层裙房连接处,对于超长的多层或高层框架结构,虽不存在差异沉降问题,但为解决钢筋混凝土的收缩变形或混凝土的收缩应力,也采用后浇收缩带或后浇温度带,因此,后浇带的施工问题应引起高度重视,后浇带应按设计要求预留,一定要留企口缝,并按规定时间灌注混凝土,灌注前应将表面清理干净,将钢筋加以整理或施焊,然后浇注早强、无收缩水泥配制的混凝土或膨胀混凝土,浇注后加强养护。施工中要采取有力措施,加强监督与检查,以确保后浇带的施工质量。