论文部分内容阅读
如何协调大型火力发电机组的安装和调试关系 ,保证机组调试和试运的进度 ,一直以来是相当棘手的问题。为此 ,引进一种新的管理办法———系统安装完成移交调试的管理过程 (以下简称STOCC) ,以便更有效地对整个安装和调试过程进行进度管理。并且为了推广应用 ,介绍了沙角C电厂工程实行STOCC管理的经验以及国产机组工程安装引进STOCC管理的具体做法及产生的效果。
How to coordinate the installation and commissioning relationship of large-scale thermal power generating units and ensure the progress of unit commissioning and trial operation has always been a very difficult problem. To this end, the introduction of a new management approach --- the system is installed to complete the transfer of the management process (hereinafter referred to as STOCC), in order to more effectively the entire installation and commissioning process for progress management. In order to promote the application, the experience of implementing STOCC management in the Shajiao C Power Plant project and the specific practices and effects of the introduction of the STOCC management for the installation of the domestic unit engineering were introduced.